Q1. Start molding specimens for strength tests within 30 minutes after fabricating the
composite sample.
A. True
B. False - correct answer B. False
ASTM C172 -Para (4.1.2) - Start molding.
specimens for strength tests within 15 min after fabricating the
composite sample.
Q2. The maximum allowable time between obtaining the first and last portions of the
composite sample may not exceed 5 minutes.
,A. True
B. False - correct answer B. False
ASTM C172 - Para (4.1)- The elapsed time shall not exceed 15 min. between obtaining
the first and final portions of the composite sample.
Q3. The composite concrete sample must be protected from sun, wind, contamination
and rapid evaporation.
A. True
B. False - correct answer A. True
ASTM C172 - Para (4.1.2)
,Q4. If the concrete contains aggregates larger than those that are appropriate for a
size of mold or equipment used, the sample should be wet sieved before making the
test.
A. True
B. False - correct answer A. True
ASTM C172- Para (6.1)
Q5. The composite sample should not be remixed before beginning any tests.
A. True
B. False - correct answer B. False
, ASTM C172-Para (4.1.1) -The sample shall be combined and remixed with a shovel the
minimum amount necessary to ensure uniformity and compliance with the maximum
time limits
Q6. Sampling should normally be performed, as the concrete is discharged from the
mixer.
A. True
B. False - correct answer B. False
ASTM C172-Para (5). NOTE 2—Sampling should normally be performed as the concrete
is delivered from the mixer.
To the conveying vehicle used to transport the