What is NYC Chapter 33?
What is Section 3301 and 3302?
Ans: Ch 33 = Safeguards During Construction or Demoltion
3301 = General
3302 = Definitions
Assignment Expert
What do you do when code does not specifically state inspection is
Guru01 - Stuvia
needed on an equipment?
Ans: [3301.4.1]
Any equipment (except hand tools) that affects safety of public or
2026
property shall be inspected by a COMPETENT PERSON designated by the
contractor using the equipment
©
This inspection shall be documented in an inspection checklist signed
and dated by the CP
Who is responsible for maintaining construction/demo signs?
Ans: [3301.9]
The permit holder for the construction/demo work
If no active permits, then the building owner
Name the (8) items that need to be listed on a Project Information Panel
Ans: [3301.9.1]
1. Rendering, elevation drawing, or zoning diagram
, 2 for specific request mail
2. "Work in Progress" Title and specifying zoning use
3. Anticipated project completion date
4. Property owner's corporate name, address, phone #
5. Website address or phone # to contact
6. GC name and phone #
7. "To anonymously report unsafe conditions..call 311" in English and
Assignment Expert
Spanish
8. Primary project permit (laminated)
Guru01 - Stuvia
Where should the Project Information Panel be posted?
How high up?
2026
Ans: [3301.9.1.2]
©
On the fence on each perimeter
-if the perimeter is greater than 150ft, post at each corner
- posted 4ft high from the ground to the bottom edge of the panel
Name the specs of the Project Information Panel and the (2) exceptions
Ans: [3301.9.1.4]
6 ft wide x 4 ft high
Exceptions:
1) for demo project = 2'-4" wide x 4ft high
, 3 for specific request mail
2) Sites that have street frontage less than 60 ft = 55" wide x 36.5" high
What contents should be on the SWS parapet info panel? (3)
Ans: [3301.9.2.1]
1) Street address of the site
2) Name of contractor responsible for site...if not, then the owner
3) The statement "For more info, visit NYC.GOV/BUILDINGS"
Assignment Expert
Name the (4) requirements of posting SWS parapet info panel
Ans: [3301.9.2.2]
Guru01 - Stuvia
1) Posted along the long axis of the SWS
2) Shall not be posted above/below parapet
2026
3) Between 3-6 feet from the left edge SWS or property line
©
4) Centered above project info panel on Fence
What dimension shall the SWS parapet info panel be?
Ans: [3301.9.2.4]
3 ft high x 6 ft wide
When do you need site safety orientation and refresher?
Ans: [3301.11]
- Orientation needed for each worker at any site that requires
SSM/SSC/superintendent
- Refresher is needed after (1) year for each worker still working at the
same site
, 4 for specific request mail
Who can conduct the site safety orientation and refresher?
Ans: [3301.11.3]
A qualified person designated by the permit holder
This qualified person shall have ability to communicate with each worker
What contents should be included in site safety orientation and
refresher?
Ans: [3301.11.4]
Assignment Expert
1) A review of safety procedures and any hazardous activities to be
performed at the site
Guru01 - Stuvia
2) Information pertaining to site safety training SST as required in Section
3321
2026
Describe how the site safety orientation and refresher is recorded
Ans: [3301.11.5]
©
Records shall be maintained by permit holder and kept at the jobsite
1) Date and time of orientation/refresher
2) Name, title, and company of each worker
3) Name, title, company, and signature of the qualified person who
conducted the orientation
What are the contents of a pre-shift meeting? Who can conduct them?
Ans: [3301.12]
- Shall include review of activities and tasks to be performed during the
workshift, including specific safety concerns or risks
SSM Questions | Accurate & Verified Answers to Pass
Actual Exam
What is NYC Chapter 33?
What is Section 3301 and 3302?
Ans: Ch 33 = Safeguards During Construction or Demoltion
3301 = General
3302 = Definitions
Assignment Expert
What do you do when code does not specifically state inspection is
Guru01 - Stuvia
needed on an equipment?
Ans: [3301.4.1]
Any equipment (except hand tools) that affects safety of public or
2026
property shall be inspected by a COMPETENT PERSON designated by the
contractor using the equipment
©
This inspection shall be documented in an inspection checklist signed
and dated by the CP
Who is responsible for maintaining construction/demo signs?
Ans: [3301.9]
The permit holder for the construction/demo work
If no active permits, then the building owner
Name the (8) items that need to be listed on a Project Information Panel
Ans: [3301.9.1]
1. Rendering, elevation drawing, or zoning diagram
, 2 for specific request mail
2. "Work in Progress" Title and specifying zoning use
3. Anticipated project completion date
4. Property owner's corporate name, address, phone #
5. Website address or phone # to contact
6. GC name and phone #
7. "To anonymously report unsafe conditions..call 311" in English and
Assignment Expert
Spanish
8. Primary project permit (laminated)
Guru01 - Stuvia
Where should the Project Information Panel be posted?
How high up?
2026
Ans: [3301.9.1.2]
©
On the fence on each perimeter
-if the perimeter is greater than 150ft, post at each corner
- posted 4ft high from the ground to the bottom edge of the panel
Name the specs of the Project Information Panel and the (2) exceptions
Ans: [3301.9.1.4]
6 ft wide x 4 ft high
Exceptions:
1) for demo project = 2'-4" wide x 4ft high
, 3 for specific request mail
2) Sites that have street frontage less than 60 ft = 55" wide x 36.5" high
What contents should be on the SWS parapet info panel? (3)
Ans: [3301.9.2.1]
1) Street address of the site
2) Name of contractor responsible for site...if not, then the owner
3) The statement "For more info, visit NYC.GOV/BUILDINGS"
Assignment Expert
Name the (4) requirements of posting SWS parapet info panel
Ans: [3301.9.2.2]
Guru01 - Stuvia
1) Posted along the long axis of the SWS
2) Shall not be posted above/below parapet
2026
3) Between 3-6 feet from the left edge SWS or property line
©
4) Centered above project info panel on Fence
What dimension shall the SWS parapet info panel be?
Ans: [3301.9.2.4]
3 ft high x 6 ft wide
When do you need site safety orientation and refresher?
Ans: [3301.11]
- Orientation needed for each worker at any site that requires
SSM/SSC/superintendent
- Refresher is needed after (1) year for each worker still working at the
same site
, 4 for specific request mail
Who can conduct the site safety orientation and refresher?
Ans: [3301.11.3]
A qualified person designated by the permit holder
This qualified person shall have ability to communicate with each worker
What contents should be included in site safety orientation and
refresher?
Ans: [3301.11.4]
Assignment Expert
1) A review of safety procedures and any hazardous activities to be
performed at the site
Guru01 - Stuvia
2) Information pertaining to site safety training SST as required in Section
3321
2026
Describe how the site safety orientation and refresher is recorded
Ans: [3301.11.5]
©
Records shall be maintained by permit holder and kept at the jobsite
1) Date and time of orientation/refresher
2) Name, title, and company of each worker
3) Name, title, company, and signature of the qualified person who
conducted the orientation
What are the contents of a pre-shift meeting? Who can conduct them?
Ans: [3301.12]
- Shall include review of activities and tasks to be performed during the
workshift, including specific safety concerns or risks