5 Days - Correct answer-How many days do you have to return a sales License?
6 Members - Correct answer-How many board members are of a licensed
occupation?
The License holder - Correct answer-Who is the respondent in a formal complaint?
18 Months - Correct answer-How many months does a person have to file a
complaint against you?
Occupational Code P.A. 299 of 1980 - Correct answer-What is PA299?
Can only work in GH or Has to get all contracts approved by lawyer. - Correct
answer-What is an example of a limitation put on your license?
15 days - Correct answer-How many days do you have to respond to a complaint?
Code book - Correct answer-What is the minimal standards or acceptable practice?
True - Correct answer-The occupational code has 6 articles that apply to every
occupation and article 24 is specific to builders True or False
,True - Correct answer-A limitation can be placed on your license before or after it
is issued. True or False
True - Correct answer-The licensee has 10 days to report a change of control or
direction of a business True or False
The person that holds the license for a company - Correct answer-What is a
qualifying officer?
3 people witch 1 of them must be a Inspector - Correct answer-How many general
public people are on the board?
2, 4 Year terms - Correct answer-What is the term limit for a board member?
The Senet - Correct answer-The governor appoints a member of the board with the
advice and consent of ?
2 Terms - Correct answer-How many terms can a board member be on the board?
3 years - Correct answer-How long is a license good for?
True - Correct answer-The builders test is administered by an outside agency? True
or False
1 Builder - Correct answer-How many builders can a salesman work for at the
same time?
,Yes - Correct answer-If your license were to laps for 3 years and 1 day, would you
have to retest?
True - Correct answer-The code book is updated every 3 years True or False
True - Correct answer-P.A. 230 of 1972 is the state construction code act? True or
False
Yes and 30 days - Correct answer-If you get a limitation put on your license can
you appeal it and what is the time limit?
42 hours - Correct answer-How many educational hours are required for your first
6 years?
3 hours - Correct answer-What is the minimum educational hours per year?
Length X Width = Area - Correct answer-Area = Length X Width
1/4" = 1' One-forty-eight size 1:48 - Correct answer-1/4" = 1' One-forty-eight size
1:48
5.7 sq ft - Correct answer-What sq ft is required for a basement Egress window
25 feet - Correct answer-The escape devices for a trench over 4 feet deep must be
within a maximum of how many feet of the worker?
1/4 = 1 inch 1:48 - Correct answer-commonly used size for scale of drawings
, 5.7 sq Feet - Correct answer-Egress window size clearance
34 - 36 inches - Correct answer-height of hand rail?
36 - 38 inches - Correct answer-Height of the door handle?
43,560 SQ FT - Correct answer-How many square feet are in 1 Acre?
b.) 5
3,000 square feet is the total square footage. Ventilation is 1/300 of total roof
square footage, which means that for every 300 square feet of roof area you need 1
foot of ventilation.
3, = 10 square feet of total ventilation required.
The ventilation will be split equally between ridge vents and soffit vents.
= 5 square feet of soffit vent required.
(5 square feet of ridge vent would also be required.) - Correct answer-The required
ventilation for a 3,000 square foot roof is 1/300 of the horizontal roof projection
Answers Graded A+
5 Days - Correct answer-How many days do you have to return a sales License?
6 Members - Correct answer-How many board members are of a licensed
occupation?
The License holder - Correct answer-Who is the respondent in a formal complaint?
18 Months - Correct answer-How many months does a person have to file a
complaint against you?
Occupational Code P.A. 299 of 1980 - Correct answer-What is PA299?
Can only work in GH or Has to get all contracts approved by lawyer. - Correct
answer-What is an example of a limitation put on your license?
15 days - Correct answer-How many days do you have to respond to a complaint?
Code book - Correct answer-What is the minimal standards or acceptable practice?
True - Correct answer-The occupational code has 6 articles that apply to every
occupation and article 24 is specific to builders True or False
,True - Correct answer-A limitation can be placed on your license before or after it
is issued. True or False
True - Correct answer-The licensee has 10 days to report a change of control or
direction of a business True or False
The person that holds the license for a company - Correct answer-What is a
qualifying officer?
3 people witch 1 of them must be a Inspector - Correct answer-How many general
public people are on the board?
2, 4 Year terms - Correct answer-What is the term limit for a board member?
The Senet - Correct answer-The governor appoints a member of the board with the
advice and consent of ?
2 Terms - Correct answer-How many terms can a board member be on the board?
3 years - Correct answer-How long is a license good for?
True - Correct answer-The builders test is administered by an outside agency? True
or False
1 Builder - Correct answer-How many builders can a salesman work for at the
same time?
,Yes - Correct answer-If your license were to laps for 3 years and 1 day, would you
have to retest?
True - Correct answer-The code book is updated every 3 years True or False
True - Correct answer-P.A. 230 of 1972 is the state construction code act? True or
False
Yes and 30 days - Correct answer-If you get a limitation put on your license can
you appeal it and what is the time limit?
42 hours - Correct answer-How many educational hours are required for your first
6 years?
3 hours - Correct answer-What is the minimum educational hours per year?
Length X Width = Area - Correct answer-Area = Length X Width
1/4" = 1' One-forty-eight size 1:48 - Correct answer-1/4" = 1' One-forty-eight size
1:48
5.7 sq ft - Correct answer-What sq ft is required for a basement Egress window
25 feet - Correct answer-The escape devices for a trench over 4 feet deep must be
within a maximum of how many feet of the worker?
1/4 = 1 inch 1:48 - Correct answer-commonly used size for scale of drawings
, 5.7 sq Feet - Correct answer-Egress window size clearance
34 - 36 inches - Correct answer-height of hand rail?
36 - 38 inches - Correct answer-Height of the door handle?
43,560 SQ FT - Correct answer-How many square feet are in 1 Acre?
b.) 5
3,000 square feet is the total square footage. Ventilation is 1/300 of total roof
square footage, which means that for every 300 square feet of roof area you need 1
foot of ventilation.
3, = 10 square feet of total ventilation required.
The ventilation will be split equally between ridge vents and soffit vents.
= 5 square feet of soffit vent required.
(5 square feet of ridge vent would also be required.) - Correct answer-The required
ventilation for a 3,000 square foot roof is 1/300 of the horizontal roof projection