(A) Agreement between owner and contractor, conditions of
Correct Answers the contract, drawings, and specifications,
addenda and modifications, other documents listed in the
agreement. (B) Agreement between owner and contractor,
conditions of the contract, drawings and specifications, project
manual, shop drawings.
(A) Correct Answers 1, 2, 3, 4, 5.
(A) Correct Answers 1, 2, 3, 4, 5.
(A) Correct Answers Adversarial
(A) Correct Answers As built drawings.
(A) Correct Answers Bidding requirements.
(A) Correct Answers By the Owner's direct selection
(A) Correct Answers Change order.
(A) Correct Answers CMa
(A) Correct Answers Conception
(A) Correct Answers Continue footing excavation and call the
telephone company.
(A) Correct Answers Contract documents.
,(A) Correct Answers Contract time.
(A) Correct Answers D-B-B
(A) Correct Answers Defines the relationship of the owner,
A/E, and contractor.
(A) Correct Answers Descriptive.
(A) Correct Answers Design-Build
(A) Correct Answers Due diligence studies, master planning
and
(A) Correct Answers Entitled to additional payment as the
discovery was after Substantial Completion.
(A) Correct Answers Extent, Cost and Time
(A) Correct Answers General, Materials, Installation.
(A) Correct Answers If observed before substantial completion.
(A) Correct Answers Limit competition.
(A) Correct Answers Manufacturer.
(A) Correct Answers Methods of creating drawings.
,(A) Correct Answers Modify the procurement documents
before award of the contract.
(A) Correct Answers Once a week.
(A) Correct Answers Owner
(A) Correct Answers Owner, Architect, Contractor, Supplier
(A) Correct Answers Project Initiation
(A) Correct Answers Recommend to the Owner to allow for
added payment in order to continue the Project on time.
(A) Correct Answers Require the tile subcontractor to perform
the work and bear the full cost including compensation for the
A/E's additional services, if any.
(A) Correct Answers Review and approve if the product meets
the design criteria.
(A) Correct Answers Review the drawing with the
subcontractor and make notations on the drawings of the
decisions made.
(A) Correct Answers Section 00 21 13 Instructions to Bidders
(A) Correct Answers Section 01 32 00 Construction Progress
Documentation.
(A) Correct Answers Show existing work that is to be modified.
, (A) Correct Answers Show watertight construction.
(A) Correct Answers Similar General Conditions are used for
the separate contract.
(A) Correct Answers Spec book.
(A) Correct Answers Stop all work until the A/E give clear
direction on how to proceed.
(A) Correct Answers Supplemental instructions.
(A) Correct Answers Understanding contract fulfillment
requirements.
(A) Correct Answers Workmen.
(A) Procurement requirements, which include solicitation,
Correct Answers instructions for procurement, available
information, procurement forms and supplements. (B)
Contracting requirements, which include the agreement,
performance bond, payment bond, and certificates.
(A) Written portions of the contract only. (B) Graphic portions
of the contract only. Correct Answers
(B) Correct Answers 2, 4, 5.
(B) Correct Answers 2, 4, 5.