(ESi)
(EFi)
(LFi)
(LSi)
(Ti)
(TFi)
(FFi) Correct Answers Early Activity Start
Early Activity Finish
Late Activity Finish
Late Activity Start
Duration
Total Float
Free Float
= Assigned (beginning of the day convention, 1) Correct
Answers ES
= Assigned (Usually the project finished date) Correct Answers
LF
= ES + T Correct Answers EF
= LFfi - Tfi Correct Answers LS
= LFi - ESi - Ti = LFi - EFi Correct Answers TF
= Workhours/Duration x Productivity factor Correct Answers
Adjusted Workhours/Duration
, A critical activity is the one that has
Select one:
a. No float
b. Positive float
c. Negative float
d. None of the above Correct Answers a
A precedence diagram uses nodes to represent
Select one:
a. Activities
b. Activity links
c. Resources
d. Time Correct Answers a
A significant difference between "planning" and "scheduling" is:
Correct Answers Scheduling determines when to do, and
planning determines what to do, how to do and by whom.
Activities (5) Correct Answers -consume time
-usually consume resources
-have a definable start and finish
-are assignable
-are measurable
After removing the redundant dependencies, the list of activities
is called Correct Answers IPA (Immediate Preceding [come
before] Activities)
An event doesn't consume or materials Correct Answers time