What is NYC Chapter 33?
What is Section 3301 and 3302? - ANS Ch 33 = Safeguards During Construction or Demoltion
3301 = General
3302 = Definitions
What do you do when code does not specifically state inspection is needed on an equipment? -
ANS [3301.4.1]
Any equipment (except hand tools) that affects safety of public or property shall be inspected by
a COMPETENT PERSON designated by the contractor using the equipment
This inspection shall be documented in an inspection checklist signed and dated by the CP
Who is responsible for maintaining construction/demo signs? - ANS [3301.9]
The permit holder for the construction/demo work
If no active permits, then the building owner
@COPYRIGHT 2026/2027 ALL RIGHTS RESERVED
1
,Name the (8) items that need to be listed on a Project Information Panel - ANS [3301.9.1]
1. Rendering, elevation drawing, or zoning diagram
2. "Work in Progress" Title and specifying zoning use
3. Anticipated project completion date
4. Property owner's corporate name, address, phone #
5. Website address or phone # to contact
6. GC name and phone #
7. "To anonymously report unsafe conditions..call 311" in English and Spanish
8. Primary project permit (laminated)
Where should the Project Information Panel be posted?
How high up? - ANS [3301.9.1.2]
On the fence on each perimeter
-if the perimeter is greater than 150ft, post at each corner
- posted 4ft high from the ground to the bottom edge of the panel
Name the specs of the Project Information Panel and the (2) exceptions - ANS [3301.9.1.4]
6 ft wide x 4 ft high
Exceptions:
1) for demo project = 2'-4" wide x 4ft high
2) Sites that have street frontage less than 60 ft = 55" wide x 36.5" high
What contents should be on the SWS parapet info panel? (3) - ANS [3301.9.2.1]
1) Street address of the site
2) Name of contractor responsible for site...if not, then the owner
@COPYRIGHT 2026/2027 ALL RIGHTS RESERVED
2
, 3) The statement "For more info, visit NYC.GOV/BUILDINGS"
Name the (4) requirements of posting SWS parapet info panel - ANS [3301.9.2.2]
1) Posted along the long axis of the SWS
2) Shall not be posted above/below parapet
3) Between 3-6 feet from the left edge SWS or property line
4) Centered above project info panel on Fence
What dimension shall the SWS parapet info panel be? - ANS [3301.9.2.4]
3 ft high x 6 ft wide
When do you need site safety orientation and refresher? - ANS [3301.11]
- Orientation needed for each worker at any site that requires SSM/SSC/superintendent
- Refresher is needed after (1) year for each worker still working at the same site
Who can conduct the site safety orientation and refresher? - ANS [3301.11.3]
A qualified person designated by the permit holder
This qualified person shall have ability to communicate with each worker
What contents should be included in site safety orientation and refresher? - ANS [3301.11.4]
1) A review of safety procedures and any hazardous activities to be performed at the site
2) Information pertaining to site safety training SST as required in Section 3321
Describe how the site safety orientation and refresher is recorded - ANS [3301.11.5]
Records shall be maintained by permit holder and kept at the jobsite
@COPYRIGHT 2026/2027 ALL RIGHTS RESERVED
3
VERIFIED 2026.
What is NYC Chapter 33?
What is Section 3301 and 3302? - ANS Ch 33 = Safeguards During Construction or Demoltion
3301 = General
3302 = Definitions
What do you do when code does not specifically state inspection is needed on an equipment? -
ANS [3301.4.1]
Any equipment (except hand tools) that affects safety of public or property shall be inspected by
a COMPETENT PERSON designated by the contractor using the equipment
This inspection shall be documented in an inspection checklist signed and dated by the CP
Who is responsible for maintaining construction/demo signs? - ANS [3301.9]
The permit holder for the construction/demo work
If no active permits, then the building owner
@COPYRIGHT 2026/2027 ALL RIGHTS RESERVED
1
,Name the (8) items that need to be listed on a Project Information Panel - ANS [3301.9.1]
1. Rendering, elevation drawing, or zoning diagram
2. "Work in Progress" Title and specifying zoning use
3. Anticipated project completion date
4. Property owner's corporate name, address, phone #
5. Website address or phone # to contact
6. GC name and phone #
7. "To anonymously report unsafe conditions..call 311" in English and Spanish
8. Primary project permit (laminated)
Where should the Project Information Panel be posted?
How high up? - ANS [3301.9.1.2]
On the fence on each perimeter
-if the perimeter is greater than 150ft, post at each corner
- posted 4ft high from the ground to the bottom edge of the panel
Name the specs of the Project Information Panel and the (2) exceptions - ANS [3301.9.1.4]
6 ft wide x 4 ft high
Exceptions:
1) for demo project = 2'-4" wide x 4ft high
2) Sites that have street frontage less than 60 ft = 55" wide x 36.5" high
What contents should be on the SWS parapet info panel? (3) - ANS [3301.9.2.1]
1) Street address of the site
2) Name of contractor responsible for site...if not, then the owner
@COPYRIGHT 2026/2027 ALL RIGHTS RESERVED
2
, 3) The statement "For more info, visit NYC.GOV/BUILDINGS"
Name the (4) requirements of posting SWS parapet info panel - ANS [3301.9.2.2]
1) Posted along the long axis of the SWS
2) Shall not be posted above/below parapet
3) Between 3-6 feet from the left edge SWS or property line
4) Centered above project info panel on Fence
What dimension shall the SWS parapet info panel be? - ANS [3301.9.2.4]
3 ft high x 6 ft wide
When do you need site safety orientation and refresher? - ANS [3301.11]
- Orientation needed for each worker at any site that requires SSM/SSC/superintendent
- Refresher is needed after (1) year for each worker still working at the same site
Who can conduct the site safety orientation and refresher? - ANS [3301.11.3]
A qualified person designated by the permit holder
This qualified person shall have ability to communicate with each worker
What contents should be included in site safety orientation and refresher? - ANS [3301.11.4]
1) A review of safety procedures and any hazardous activities to be performed at the site
2) Information pertaining to site safety training SST as required in Section 3321
Describe how the site safety orientation and refresher is recorded - ANS [3301.11.5]
Records shall be maintained by permit holder and kept at the jobsite