1. The law that set into place stormwater regula- The Clean Water Act
tions in the 1970s is
2. Regulations for managing stormwater activity NPDES
on a construction site are outlined in the
3. When should you read and understand your Immediately after the project awarded
project stormwater pollution prevention plan and before you begin any site work is
4. Which of the following is not an allowable Discharges are contaminated ground-
stormwater discharge or non-stormwater dis- water
charge
5. Construction activity may begin When the jurisdiction of operation
specifies you can start
6. Waters that sell anti-degration standards are 303D
placed on the list
7. SWPP certifications are signed by An oflcer of the project owner or an
oflcer of the general contractor.
8. TRUE OR FALSE: The document that must be False
completed signed and submitted to the state
to obtain authorization to discharge is the NOT
9. The notice of termination can be filed when All construction inside and outside of
the building is completed and the final
stabilization has been verified as com-
plete
10. Operators on a construction site are the entity Is in charge of daily activities
in charge of plans and specifications and the
entity who is
1/8
, SWPPP Test Questions And Answers For A+ Score 2026!!
11. You should have a SWPPP for your construc- 1. Its documents stormwater manage-
tion site because (3 reasons) ment
2. Demonstrates your intent to manage
stormwater on your site
3. It is required by law
12. A well constructed SWPPP for your site should Site specific
be
13. The NO must be submitted Prior to you commencing construction
14. One necessary component of a good SWPPP is A schedule of activities
15. Factors that may impact the SWPPP schedul- Weather and climate
ing activities include
16. Pollutant sources on a construction site may 1. petroleum storage tanks
include (3) 2. Masonry material
3. soil amendment
17. The following considerations may be incorpo- Endangered species and historical
ratedd into SWPPP preservation
18. If you beileve BMP modifications are neces- Seek written approval of the project
sary onsite you must, SWPPP designer and project owner
19. The SWPPP will contain the following (3) 1. Erosion and sediment control bet
management practices
2. A site specific sequence of construc-
tion activiites
3. site maps
20. Deficit and fialed BMP's and repair
2/8