1. Clean Water Act Law set into place in 1970 for storm
water regulation
2. NPDES Regulations for monitoring storm wa-
ter activity on a construction site, are
outlined in
3. Immediately after project is awarded and be- When should you read and under-
fore you begin any site work stand SWPP
4. Contaminated ground water What is not an allowable storm wa-
ter discharge or non-storm water dis-
charge
5. When jurisdiction of operations specifies you When may construction activity begin
can start
6. 303D list Waters that fail anti-degradation list
are placed on which list.
7. An officer and project owner SWPPPs certification are signed by
who
8. FALSE The document that must be complet-
ed signed and submitted to the state
to obtain authorization to discharge is
the NOT. (T/F)
9. All construction has been completed both in- NOT can be filed when
side and outside
10. is in charge of daily activities Operations on a construction site are
the entity in charge of plans and spec-
ification and the entity who?
, SWPPP study guide questions and answers | 100% verified 2026!!
11. Stay out of trouble with the law Motives for staying in compliance with
storm water objectives?
12. To protect and preserve beneficial use of U.S. Objectives of the clean water act are
waters, maintaining their clean, physical and
biological integrity
13. National Pollutant Discharge Elimination Sys- NPDES stands for
tem
14. Site description and maps, inspection and Which are a component of a good SW-
maintenance procedure. Potential pollutant PPP
sources, schedules of activities, site contact in-
formation, plan certification documents, site
contact info and descriptions of controls BMP
15. False Construction sediment is not consid-
ered a potential pollutant source (T/F)
16. Project owner, SWPPP designer When modifying or substituting a
storm water BMP the contractor must
consult with
17. False NOI must be submitted to the appro-
priate agency before the storm water
pollution preventive plan is developed
(T/F)
18. False, 303d List Name of the list with impaired waters
is called totally daily maximum load
(T/F)
19.