date!!!
1. Clean Water Act 1970s law that set into place the regulation of
stormwater
2. NPDES Requirements for managing stormwater activity on a
construction site are outlined in the following regula-
tion
3. Immediately after the project award Onsite stormwater pollution prevention plan (SWPPP)
and before the general contractor binder should be put together by the general con-
begins any site work tractor
4. Flushing a spill down the storm drain Which of the following is not a beneficial use of water
5. Discharge from contaminated Which of the following is never an allowable stormwa-
ground water ter discharge from a construction site.
6. All construction activity, inside and The notice of termination (NOT) can be filed when
outside the building is complete and
permanent stabilization has been
verified is adequate to meet permit
requirements
7. All of the above You should have a SWPPP for construction because
8. Site Specific A well designed SWPPP should be
9. After the SWPPP is prepared and be- The stormwater notice of intent (NOI) must be sub-
fore starting construction mitted
10. All of the above Potential pollutant sources stored on a construction
site may include
11.
1/6
, Walmart SWPPP Exam Questions With All Correct Answers 2026 Latest Up
date!!!
Seek written approval from the pro- If you believe stormwater BMP modifications are nec-
ject SWPPP designer and, if required, essary, you must
the project owner
12. The SWPPP Certification Letter The document is in the SWPPP that certifies a general
contractors commitment to compliance with the SW-
PPP is
13. Protects the site by coordinating tim- Sequencing and scheduling BMP installation
ing with construction activities and
minimizing pollutant exposure
14. Account for the time it takes to install Factors to consider when creating your schedule in-
and/or implement BMPs between clude
each phase of construction
15. Note Locations and dates of installa- When installing BMP controls
tion on the site map
16. SWPPS BMPs and the construction Stormwater issues typically discussed during the
schedule stormwater/SWPPP preconstruction meeting in-
clude, among others
17. downslope of construction areas pri- Sediment control devices must be installed
or to starting land disturbing activi-
ties
18. Appropriate vegetative stabilization When inspecting inlet protection look for all but the
following
19. Temporary stabilization if they will Soil stockpiles and other disturbed areas must receive
remain inactive for more than 14
2/6