2026 | ACTUAL EXAM QUESTIONS WITH VERIFIED ANSWERS |
GRADED A+ | LATEST UPDATE 2026/2027 | BRAND NEW!!
The Clean Water Act - ✔✔✔ Correct Answer > The 1970's law that set into
place the regulation of storm water
NPDES - ✔✔✔ Correct Answer > Requirements for managing storm water
activity on a construction site are outlined in the following regulation
Discharge From Contaminated Ground Water - ✔✔✔ Correct Answer > Never
an allowable discharge from a construction site
Potential pollutant sources stored on a construction site may include? -
✔✔✔ Correct Answer > Petroleum storage tanks, fertilizer, lime, and masonry
materials.
, The SWPPP implementation sequence may be modified? - ✔✔✔ Correct
Answer > After consulting with the project SWPPP designer (CEC) and if
required, the project owner and receiving written approval.
A SWPPP site map will show all of the following? - ✔✔✔ Correct Answer >
Location of BMP's, Phasing & Sequence, Limits of Disturbance
A notice of termination can be filed when? - ✔✔✔ Correct Answer > All
construction activity, inside and outside of the building is complete.
Permanent stabilization has been verified.
The storm water notice of intent must be submitted? - ✔✔✔ Correct Answer >
After the SWPPP is prepared and before starting construction.
Which of the following information is to be posted at the entrance to