Practice Exam Questions And Correct
Answers (Verified Answers) Plus
Rationales 2026
1. What is the primary purpose of a boiler inspection?
|| || || || || || || ||
A. Improve fuel efficiency || ||
B. Assess operator performance
|| ||
C. Ensure the safe operation of the boiler
|| || || || || ||
D. Reduce water usage || ||
The main goal of inspection is to prevent hazardous conditions
|| || || || || || || || ||
||and ensure the boiler operates safely.
|| || || || ||
2. According to Texas regulations, how often must high-pressure
|| || || || || || ||
||boilers be inspected internally?
|| || ||
A. Every 6 months || ||
B. Annually
C. Every 2 years || ||
D. Every 3 years || ||
High-pressure steam boilers require internal inspections at least
|| || || || || || ||
||once per year.
|| ||
,3. What document establishes the rules for the construction of
|| || || || || || || ||
new boilers?
|| ||
A. ASME Section II || ||
B. NFPA 85 ||
C. ASME Boiler and Pressure Vessel Code Section I
|| || || || || || ||
D. API 510 ||
ASME Section I outlines construction requirements for power boilers.
|| || || || || || || ||
4. What type of test is typically conducted to verify the integrity
|| || || || || || || || || ||
||of a repaired pressure boundary?
|| || || ||
A. Ultrasonic Test ||
B. Radiographic Test ||
C. Hydrostatic Test ||
D. Magnetic Particle Test || ||
Hydrostatic tests are standard for pressure boundary integrity
|| || || || || || ||
||verification after repairs. || ||
5. Which device prevents overpressure in a boiler?
|| || || || || ||
A. Water level gauge || ||
B. Blowdown valve ||
C. Safety valve ||
D. Economizer
Safety valves release steam to maintain pressure within safe limits.
|| || || || || || || || ||
6. What is the minimum size of a safety valve discharge outlet for a
|| || || || || || || || || || || ||
||200 psi power boiler?
|| || ||
A. 1 inch||
B. 2.5 inches ||
C. 3 inches
||
D. 4 inches
||
Discharge sizes are regulated based on pressure and capacity per
|| || || || || || || || ||
||ASME standards. ||
, 7. Which of the following is not a type of non-destructive
|| || || || || || || || ||
||examination (NDE)? ||
A. Radiographic testing ||
B. Magnetic particle testing || ||
C. Ultrasonic testing ||
D. Destructive bend testing || ||
Destructive tests are not NDE since they damage the component
|| || || || || || || || ||
||being tested. ||
8. What should be checked before performing a hydrostatic test?
|| || || || || || || ||
A. Fuel line pressure|| ||
B. Exhaust damper position || ||
C. Temperature and pressure relief valve operation || || || || ||
D. Flame scanner alignment || ||
All relief valves must be verified to avoid overpressurizing during
|| || || || || || || || ||
||the test.||
9. What does the acronym “NB” stamp indicate?
|| || || || || ||
A. Non-boiler use ||
B. National Board certification || ||
C. National Bonding ||
D. Nuclear Boiler code || ||
The “NB” stamp is applied to pressure vessels registered with the
|| || || || || || || || || ||
||National Board. ||
10. What must an inspector do when they find a
|| || || || || || || ||
hazardous condition on a boiler?
|| || || || ||
A. Note it in the inspection report only
|| || || || || ||
B. Inform the operator to monitor it
|| || || || ||
C. Condemn or tag out the boiler || || || || ||
D. Wait until the next inspection
|| || || ||