QUESTIONS AND CORRECT ANSWERS | NEWEST UPDATE 2026-
2027 | GRADED A+ | ASSURED PASS.
A notice of termination can be filed when? - correct answer- All
construction activity, inside and outside of the building is complete.
Permanent stabilization has been verified.
A SWPPP site map will show all of the following? - correct answer-
Location of BMP's, Phasing & Sequence, Limits of Disturbance
NPDES (National Pollutant Discharge Elimination System) - correct
answer- Requirements for managing storm water activity on a
construction site are outlined in the following regulation?
Potential pollutant sources stored on a construction site may include? -
correct answer- Petroleum storage tanks, fertilizer, lime, and masonry
materials.
Common types of erosion include? - correct answer- Gully, Sheet,
and Rill
Discharge From Contaminated Ground Water - correct answer-
Never an allowable discharge from a construction site
, NPDES - correct answer- Requirements for managing storm water
activity on a construction site are outlined in the following regulation
Proper spill management should include all of the following? - correct
answer- Fully stocked, proper location, signage, and labeling.
Runoff controls include? - correct answer- Diversions, check dams,
slope drains
The best location for portable toilets on your construction site is? -
correct answer- On level ground, in low construction traffic areas.
The Clean Water Act - correct answer- The 1970's law that set into
place the regulation of storm water
The contractor has the most control over what erosion rate factor? -
correct answer- Groundcover