CON 237 SIMPLIFIED ACQUISITION
PROCEDURES EXAM 2026 WITH
QUESTIONS AND ANSWERS
You have a requirement to buy a large commercially available,
prefabricated wash rack for your installation. The catalog price is $102,000.
- correct answer-Simplified acquisition procedures can be used
The Director of training for the installation has a request to purchase 25
televisions and 25 DVD recorders for the new training facility that will open
next month. Each television will cost approximately $525, and each DVD
recorder about $150. - correct answer-Simplified acquisition procedures
can be used
You have a requirement for four military-unique fighter aircraft parts. Each
part is estimated to cost 1.6 million. - correct answer-Simplified acquisition
procedures CANNOT be used.
You have a requirement to purchase equipment that was previously
developed at Government expense and sold exclusively to the military. This
type of item is: - correct answer-A non-developmental item
Evaluation factors are: - correct answer-Stated in the solicitation
, 2 |Page
An oral solicitation may be used for: - correct answer-Construction less
than $2,000
The required sources of supplies and services can be found in: - correct
answer-FAR Part 8
You have a requirement for ship repair that will require a unique welding
technique. You only know of a few firms that have performed this technique
and selecting an inexperienced contractor could be disastrous. As such,
you should primarily consider evaluating offerors': - correct answer-
Experience
When making a commercial purchase, you may conduct an in-process
inspection: - correct answer-At ay time to check that the product being
made fits your specification
When no other exceptions apply, is a Government Point of Entry (GPE)
synopsis required for purchases estimated to exceed $25,000 but not to
exceed the simplified acquisition threshold? - correct answer-YES
Market research is performed - correct answer-To determine if commercial
or non-developmental items are available to satisfy agency needs