Scope of Work (SOW) - ✔✔Covers the requirements for the ICT systems team and lists the
|| || || || || || || || || || || || || || || ||
elements of the installation.
|| || ||
Submittals - ✔✔A form of communication between the contractor and owner defining the
|| || || || || || || || || || || || ||
specifics of how a job will be undertaken.
|| || || || || || ||
Contract - ✔✔A written document that states the legal obligations of the customer and the
|| || || || || || || || || || || || || || ||
contractor.
Material List - ✔✔Contains all of the installation items by description, catalog number,
|| || || || || || || || || || || || ||
quantity, unit price, and total price.
|| || || || ||
Project Log - ✔✔A place to record detailed notes on any issues that arise.
|| || || || || || || || || || || || ||
Contract Documents - ✔✔Drawings, specs, material list, Scope of Work.
|| || || || || || || || ||
Project Schedule - ✔✔List of milestones, activities, and deliverables.
|| || || || || || || ||
Project Documents - ✔✔Project logs, acceptance plan, RFI, change orders, and closeout
|| || || || || || || || || || || ||
documents.
Site Survey - ✔✔verify installation information.
|| || || || ||
Safety Plan - ✔✔Review and incorporate the correct safety plan.
|| || || || || || || || ||
,RCP (drawing) - ✔✔Reflected ceiling plan.
|| || || || ||
A drawing - ✔✔Architectural drawings. A plan (top view) of each floor in a building.
|| || || || || || || || || || || || || ||
M drawing - ✔✔Mechanical drawings. HVAC routing, air handler units, and water piping.
|| || || || || || || || || || || ||
E drawing - ✔✔Electrical Drawing.
|| || || ||
P drawing - ✔✔Plumbing drawing.
|| || || ||
FP drawing - ✔✔Fire protection drawing.
|| || || || ||
T drawing - ✔✔Telecommunication drawing
|| || || ||
S drawing - ✔✔Structural drawing.
|| || || ||
T0 drawing - ✔✔cover page/campus plan
|| || || || ||
T1 drawing - ✔✔Floor plan, layout, and locations.
|| || || || || || ||
T2 drawing - ✔✔serving zones.
|| || || ||
T3 drawing - ✔✔Equipment room drawings.
|| || || || ||
T4 drawing - ✔✔Detail drawings.
|| || || ||
, T5 - ✔✔cable schedule/IDS (homerun tracking sheet)
|| || || || || ||
Punch List - ✔✔Formal listing of items or issues needing resolution before the project is
|| || || || || || || || || || || || || || ||
designated as complete. Needs to clearly define the specific steps or work tasks that need to be
|| || || || || || || || || || || || || || || || ||
completed.
Which drawing indicates the size and route of the HVAC system ducts, air handler units,
|| || || || || || || || || || || || || || ||
chilled water piping, and refrigerant piing within the structures? - ✔✔M drawing
|| || || || || || || || || || || ||
(mechanical).
Which drawing shows the campus or site plans exterior pathways and interbuilding systems?
|| || || || || || || || || || || || ||
- ✔✔T0 drawing
|| ||
What important document covers the requirements, lists all of the elements of the
|| || || || || || || || || || || || ||
installation, and is usually generated by the customer or the designer? - ✔✔Scope of Work
|| || || || || || || || || || || || || || ||
(SoW)
Which document is used to request clarification, supplemental information, or approval of
|| || || || || || || || || || || ||
materials substitution? - ✔✔RFI form (request for information).
|| || || || || || ||
What document is a formal listing of items or issues needing resolution before the project is
|| || || || || || || || || || || || || || || ||
designated as complete? - ✔✔Punch list. || || || || ||
Material storage sites (3) - ✔✔Work site, company-controlled location, distributor
|| || || || || || || || ||
Which meeting occurs after the initial construction meeting that discusses all aspects related
|| || || || || || || || || || || || ||
to the project with the PM, installation team, and appropriate contractors? - ✔✔Pre-
|| || || || || || || || || || || ||
Installation meeting. ||