ANSWERS(RATED A+)
When are annual Reports due - ANSWERSeptember 1
Definition of Sediment Yield - ANSWERAmount of eroded material that settles out at a
point in the watershed that is remote from the origin of the detached particles.
Max State Penalty - ANSWERState: $10K per day per violation, plus $10/gal of
sediment laden or polluted water discharged for each violation.
Federal: up to $24,500 per day for unintentional and $55,00 per day for knowing
violaiton
Types of Water Erosion - ANSWERSplash
Sheet
Rill
Gully
Channel
Where are acronyms found in CGP? - ANSWERAppendix 6
Where can you find what the CGP does or does not cover? - ANSWEROrder, Pages 4
and 5
Which types of construction projects are elgible for a ranfall erosivity waiver? -
ANSWERLess than 5 acres
less than 5 R value
Where are Active Treatment System (ATS) monitoring requirements found? -
ANSWERAttachment F,M
What are the NAL for Risk 2 and 3 - ANSWERpH <6.5 and >8.5
Turbidity >250 NTU
Receiving Water Monitoring Triggers - ANSWERFor Risk level 3
pH <6.0 and >9.0
Turbidity > 500 NTU
Sediment Risk levels - ANSWERLow Risk <15 tons/acre
Medium Risk >=15 and <75 tons/acre
High Risk >= 75tons/acre
5 different BMP Categories - ANSWERGood Site Management - "Housekeeping"