Question 1
Correct
Mark 1.00 out of 1.00
Read the definition below and choose a correct concept for the definition below: …….. involves predicting the way money will
be spent on the programme in order for people to decide whether or not to proceed, and in order that they can arrange to
have the cash ready at the right time. Choose the correct concept:
a. Budget estimation process.
b. Feasibility study.
c. Resource Planning.
d. Cost Management.
The correct answer is: Cost Management.
Question 2
Correct
Mark 1.00 out of 1.00
What dimension focuses on the main characteristics and functions of the goods or service?
a. Reliability.
b. Durability.
c. Performance.
d. Features.
The correct answer is: Performance.
https://mymodules.dtls.unisa.ac.za/mod/quiz/review.php?attempt=30724099&cmid=1318260 1/17
, 3/6/26, 6:28 PM Assessment 1: Attempt review
Question 3
Correct
Mark 1.00 out of 1.00
Resource Management can be divided into the following categories, EXCEPT:
a. Resource calendar.
b. Resource planning.
c. Resource leveling.
d. Resource smoothing and smoothing.
The correct answer is: Resource smoothing and smoothing.
Question 4
Correct
Mark 1.00 out of 1.00
When engaging in a resource aggravation, Project Managers must consider acquiring a particular resource rather than what
is already in the organisation’s disposal.
a. True.
b. False.
The correct answer is: True.
Question 5
Correct
Mark 1.00 out of 1.00
An organisation chart is any graphic display of the project detailing the lines of authority. Therefore, have the following
advantages:
a. The illustration of the division of work allows the responsible persons and/or bodies to be identified.
b. Financial feasibility
c. The lines of authority between a project manager and team members are demarcated.
d. The illustration of the division of work allows the responsible persons and/or bodies to be identified; and the
lines of authority between a project manager and team members are demarcated.
The correct answer is: The illustration of the division of work allows the responsible persons and/or bodies to be identified;
and the lines of authority between a project manager and team members are demarcated.