PREP 2026/2027 COMPLETE QUESTIONS
AND CORRECT DETAILED ANSWERS ||
100% GUARANTEED PASS RECENT
VERSION
1. On design build Contracts, the Contractor will receive monthly progress
payments based on? - ANSWER Monthly Estimates
2. On Conventional jobs, concrete class IV (superstructure) methos of
measurement is? - ANSWER Plan Quantities
3. Using the Current Specifications and the attached Summary Tables what is
the pay quantity for the concrete production pile? (80' authorized pile length)
- ANSWER 80 ft
4. Determine the adjusted plan quantity tonnage and the maximum tonnage that
can be paid for Miscllaneous Asphalt based on the current Specifications,
which allows a maximum pay of 105% of the adjusted plan quantity tons. (
pay to the appropriate accuracy)
Plan Quantity Area (SY) =700 SY ( no revisions)
Plan Quantity Tons: 70.0 Tons based on 2" thick per specs
Adjusted PQ Tonnage Placed =75.2 Tons from report
Gmm fromSpecs = 2.540 and Target Spread Rate =220 Lbs/SY
Gmm from Mix 1: 2.522 and tonnage- weighted Gmm=2.55 Lbs/SY -
ANSWER 69.5 Tons and max pay 73.0 Tons
, 5. Find the total thickness on a composite base which includes 4 inches of
Limerock Base and 4 inches of type B (12.5) Asphalt Base given the
following information:
Limerock Base Thickness from Core Out Report =4.19"
Asphalt (12.5) Base: Gmm =2.365 from the design mix
Average Spread Rate from the roadway report= 429 Lbs/SY - ANSWER
Gmm x 43.3 =102.9
.4 = 4.19"
4.19" + 4.19" = Total 8.38 inches
6. On an open graded Friction Course (FC-5) Pavement, a straightedge
deficiency was left in place at no pay. Calculate the equivalent tonnage at no
pay. ( Pay to the appropriate accuracy)
Lane Width =12 ft
Location of Deficiency= STA 1+56 to STA 1+67 ( 167-156=11) - ANSWER Lx
Wx .0044
L=50'+11'+50' = 111'
111' X 12' X 0.0044 = 5.9 TNS
7. Lot 3 has a Tonnage of 2529.0 tons with a Composite Pay Factor of 1.04.
What would the calculated Composite Pay Factor adjustment amount be if
the unit price is $100.00 per ton? - ANSWER (CPF-1) = Unit price
(1.04-1) $100= 4
$4/ton x 2529 tn= $10,116
8. As items in the feild are completed,within 30 days, you will need to have the
supporting documentation available to support the pay item in the? -
ANSWER Plan Summary Boxes
9. Using the current Specifications and the attached Summary Tables, what is
the pay quantity for this steel test pile? ( 60' Authorized pipe length) -
ANSWER 60'