Practice Examination Newest 2025 – 2026 Questions
From Past Papers Actual Exams Complete 100 Questions
And Correct Detailed Answers (Verified Answers)
|Already Graded A+||Brand New!!
Content Covered (Most Tested Areas Based on Official CAPM
Syllabus): Project Integration Management, Project Scope
Management, Project Schedule Management, Project Cost
Management, Project Quality Management, Project Resource
Management, Project Communications Management, Project
Risk Management, Project Procurement Management, Project
Stakeholder Management, Predictive and Agile Concepts,
Project Governance and Business Environment
1. During project initiation, the document that formally authorizes the project
and provides the project manager with authority to apply organizational
resources is called the:
A. Project management plan
B. Scope statement
C. Project charter
D. Stakeholder register
Answer: C. Project charter
The project charter officially authorizes the project and grants authority to the
project manager to begin planning and executing project activities.
, 2. Which process group includes processes required to define a new project or
phase?
A. Planning
B. Initiating
C. Executing
D. Monitoring and Controlling
Answer: B. Initiating
The Initiating Process Group establishes the project’s purpose, identifies
stakeholders, and authorizes the project.
3. A project manager is defining deliverables and boundaries of the project.
Which document is being created?
A. Work breakdown structure
B. Project scope statement
C. Project schedule
D. Risk register
Answer: B. Project scope statement
The project scope statement defines the project deliverables, boundaries,
assumptions, and constraints.
4. Which tool breaks project deliverables into smaller, manageable
components?
A. Critical path method
B. Work breakdown structure
C. Risk breakdown structure
D. Responsibility assignment matrix
Answer: B. Work breakdown structure
The WBS decomposes project deliverables into smaller work packages for easier
management.
, 5. The process of defining and documenting relationships among project
activities is known as:
A. Sequence activities
B. Estimate activities
C. Plan schedule management
D. Control schedule
Answer: A. Sequence activities
Sequencing identifies logical relationships between tasks to build the schedule
network diagram.
6. Which scheduling method identifies the longest path through the project?
A. PERT
B. Critical path method
C. Monte Carlo analysis
D. Fast tracking
Answer: B. Critical path method
The critical path is the longest sequence of activities determining the minimum
project duration.
7. A project has a planned value (PV) of $100,000 and an earned value (EV) of
$90,000. What does this indicate?
A. Project is ahead of schedule
B. Project is behind schedule
C. Project is under budget
D. Project is over budget
Answer: B. Project is behind schedule
If earned value is less than planned value, the project is behind schedule.
8. Which document lists identified risks, their characteristics, and responses?
, A. Issue log
B. Risk register
C. Stakeholder register
D. Assumption log
Answer: B. Risk register
The risk register records all identified risks, their probability, impact, and response
strategies.
9. A stakeholder with high power and high interest should be managed by:
A. Monitoring only
B. Keeping informed
C. Keeping satisfied
D. Managing closely
Answer: D. Managing closely
Stakeholders with high power and high interest require close engagement and
regular communication.
10.The process of obtaining seller responses and selecting a supplier is called:
A. Conduct procurements
B. Plan procurements
C. Control procurements
D. Close procurements
Answer: A. Conduct procurements
This process involves evaluating bids and selecting vendors.
11.Which process ensures project deliverables meet the defined quality
standards?
A. Manage quality
B. Control quality
C. Plan quality management
D. Manage communications