Changes Clause, Variation in Estimated Quantity, Differing Site Conditions (Type I
& II), Suspension of Work, Value Engineering Change Proposals (VECP), Buy
American Act Compliance, Payment and Performance Bonds, Surety Roles,
Inspection of Construction, Contractor Responsibilities, Government Remedies,
Latent and Patent Defects, Scope Determination, Foreseeability, Out-of-Scope
Actions, Acceleration vs. Expediting, BCOES Reviews, Partnering and
Collaboration, Price and Cost Analysis Techniques, Cost Realism, Certified Cost or
Pricing Data Thresholds, Default Clause, Excusable Delays, Anti-deficiency Act
(ADA), Obligations vs. Commitments, Independent Government Estimates (IGE),
Notice to Proceed (NTP), Undefinitized Change Orders (UCO), Justification &
Approval (J&A), Critical Path Analysis, Beneficial Occupancy vs. Original Contract
Completion Date, and Contract Administration Roles of ACO, KO, and PM Exam
Questions Verified and Provided with Complete A+ Graded Rationales Latest
Updated 2026
Changes can be made to the following:
(1) In the specifications (including drawings and designs);
(2) In the method or manner of performance of the work;
(3) In the Government-furnished property or services; or
(4) Directing acceleration in the performance of the work.
What 4 things can be modified under the Changes Clause
1. Is the absolute value of the change within warrant threshold of $500K?
2. Is the change for a construction contract?
3. Is the change within the scope of the contract?
,4. Is the change governed by any of the 7 authorized clauses?
4 checks for ACO to issue a mod
1. Variation in Estimate Quantity
2. Differing Site Conditions
3. Suspension of Work
4. Changes
5. Value Engineering - Construction
6. Default
7. Changes and Changed Conditions (purchase orders)
7 Clauses in which ACO may modify construction contracts
ACO Appointment Letter
Letter from the Contracting Officer that authorizes the ACO to obligate the government only
within the monetary and other limitations delegated to them for a specific contract.
Variation in Estimated Quantity Defined
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual
quantity of the unit-priced item varies more than 15 percent above or below the estimated
quantity, an equitable adjustment in the contract price shall be made upon demand of either
party.
, Variation in Estimated Quantity Clause
When a fixed-price construction contract is contemplated that authorizes a variation in the
estimated quantity of unit-priced items
Variation in Estimated Quantity Rule of Thumb
Consider economy of scale rule of thumb when evaluating variation in estimated quantity
proposals. Increase in quantity should decrease unit price
Differing Site Conditions
Clause which allows contractor to seek equitable adjustment if conditions are found to differ
materially from what is indicated in the contract or normally encountered
Differing Site Conditions Type 1
Subsurface or latent physical conditions at the site which differ materially from those indicated
in this contract
Differing Site Conditions Type 2
Unknown physical conditions at the site, of an unusual nature, which differ materially from
those ordinarily encountered and generally recognized as inhering in work of the character
provided for in the contract.