Answers 2026/2027 – Construction Quality
Management for Contractors (Verified A+ Study
Guide)
Save
Terms in this set (40)
The ______ consists of daily checks of Follow-up phase
the work to assure continuing
compliance with contract
requirements
Design-Build contracts require: The QC Manager to be in place and take an active
role in the review and coordination of the design
Which of the following is included in Safety
all three phases of the Three Phases
of Control
The purpose of Construction Quality Achieve the quality established by properly
Management is to developed requirements through the combined
responsibility, but separate, efforts of contractor
and Government personnel
, Testing is extremely important in Both the contractor and the Government
Construction Quality Management
and is performed by
The primary purpose of the Three- Require the contractor to plan, schedule, and
Phase Control System is to: perform quality management actions to assure
work meets all specified quality standards
Quality Assurance Personnel have require the contractor to maintain the quality
the responsibility to: specified in the plans and specifications
the ____ is the appropriate time to Preparatory Phase
assure that all materials and/or
equipment have been tested.
submitted, and approved.
The Preconstruction Conference and conducted prior to the commencement of any
the Coordination and Mutual physical construction work
Understanding Meeting are:
Contractor testing procedures: are specified in the technical specifications,
outlined in the Quality Control Plan, and addressed
at the Coordination and Mutual Understanding
Meeting.
The Quality Control Plan contains: Identification of individual quality control
personnel, including name, qualifications, assigned
duties, responsibilities and authorities
Tests that are unnanounced, quality assurance tests
randomly performed, and repeat
quality control tests are: