ANSWERS
|\
A full lot of super pave asphalt is what size?
|\ |\ |\ |\ |\ |\ |\ |\ |\
1,000 tons |\ |\
1,000 to 2000 tons |\ |\ |\
2000 to 4000 tons |\ |\ |\ |\
1 days production - CORRECT ANSWERS ✔✔2000 to 4000
|\ |\ |\ |\ |\ |\ |\ |\ |\
tons
Which is not typically used as an asphalt binder in fdot
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
mix designs? |\
PG 52-28 |\
PG 58-22 |\
PG 62-22 |\
PG 76-22(PMA)
|\
PG 82-22 (PMA) - CORRECT ANSWERS ✔✔PG 62-22
|\ |\ |\ |\ |\ |\ |\
Who cuts the density cores used for verification testing?
|\ |\ |\ |\ |\ |\ |\ |\
The verification technician
|\ |\
The contractor |\
The independent verification testing technician
|\ |\ |\ |\ |\
, None of the above - CORRECT ANSWERS ✔✔The
|\ |\ |\ |\ |\ |\ |\ |\
contractor
A full lot is composed of 5 sublots and 4 cores per lot T/F -
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔False
|\ |\ |\
What is the most important for consistent compaction of
|\ |\ |\ |\ |\ |\ |\ |\ |\
asphalt mix? |\
The mix is hotter in temperature
|\ |\ |\ |\ |\
The mix is colder in temperature
|\ |\ |\ |\ |\
The mix is uniform in temperature
|\ |\ |\ |\ |\
Temperature of the mix does not affect compaction - |\ |\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔The mix is uniform in |\ |\ |\ |\ |\ |\ |\
temperature
Referring to general stationing guidelines, R1 would be |\ |\ |\ |\ |\ |\ |\ |\
____ than R2 |\ |\
Closer to centerline |\ |\
Closer to outside shoulder |\ |\ |\
Closure to the inside shoulder |\ |\ |\ |\
Both A and C - CORRECT ANSWERS ✔✔Both A and C
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
While using the rolling straightedge, if the needle goes in
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
the red zone indicating an unacceptable high spot in the
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\