RPPO 2026 LATEST QUESTIONS AND
ANSWERS| ACE YOUR GRADES.
What are the 2 price systems - correct answer -Unit and net
Unit price - correct answer -Unit is receiving an item and not
having a turn-in so you will pay full price for it.
The four DLR advice codes - correct answer -5A, 5D, 5G, 5S
Net price - correct answer -Net is having a part for exchange so
the cost is reduced
5A - correct answer -Replacement of DLR which was surveyed
or is beyond repair
5D - correct answer -Initial requirement due to new or increased
allowance
, Page | 2
5G - correct answer -Exchange 1 for 1 turn in available
5S - correct answer -Remain in place certification no turn in until
replacement is received
How long do you have to turn over a Remain in Place DLR -
correct answer -24 hours
If part ordered is a DLR, what must be done? - correct answer -
Provide a turn-in for a new part = 5G; one for one exchange to the
DLR manager
Provide a Remain in Place (RIP) chit in the place of the part if the
part can't be removed along with a RIP message requesting
adding it to the RIP listing to the DLR manager
Certified Remain in Place = 5S; nothing
What are CASREPs for - correct answer -Casualty reports;
Means for reporting status of ship equipment malfunction or
deficiency to correct combat readiness posture, also states units
need for tech assist and/or replacement parts to correct casualty
, Page | 3
T/F: A CASREP can be used to order larts - correct answer -
True, can be used. It's just a report, it does not order the parts
How to document material receipts - correct answer -Circle
quantity if correct
If quantity not correct, line out quantity and write in correct
quantity
Sign, print and date
How to properly identify and handle HAZMAT - correct answer -
SAFETY DATA SHEET
explains how to handle HAZMAT
What PPE to wear
Measures to take to protect yourself from HAZMAT
Disposal methods of the particular type of HAZMAT
What is an Internal MOV - correct answer -Internal Material
Obligation Validation; ensures requisitions in Material Outstanding
File are valid. Performed monthly no later than 5th of every