(CSLB) Business And Law Practice Exam
Questions And Correct Answers
1. What is the primary purpose of the Contractors State License Board
(CSLB)?
A. To collect construction taxes
B. To license and regulate contractors to protect the public
C. To set construction material prices
D. To provide construction training
Correct Answer: B. The CSLB exists to license and regulate contractors and
enforce state laws to protect consumers and ensure industry standards.
2. Which business structure provides limited liability protection to its
owners?
A. Sole proprietorship
B. General partnership
C. Corporation
D. Joint venture
Correct Answer: C. A corporation is a separate legal entity, shielding
owners from personal liability.
, 3. How long is a California contractor license valid before renewal?
A. 1 year
B. 2 years
C. 3 years
D. 5 years
Correct Answer: B. CSLB contractor licenses must be renewed every two
years.
4. What is the minimum bond amount required for a California
contractor license?
A. $10,000
B. $15,000
C. $25,000
D. $50,000
Correct Answer: C. California requires a $25,000 contractor license bond to
protect consumers.
5. Which document outlines the scope of work, price,
and responsibilities of both parties?
A. Invoice
B. Contract
C. Change order
, D. Estimate
Correct Answer: B. A contract defines the agreed terms and obligations of
both contractor and client.
6. What must a home improvement contract include to be valid in
California?
A. Verbal agreement only
B. Client’s social security number
C. Three-day right to cancel notice
D. Notary seal
Correct Answer: C. California law requires a notice of the homeowner’s
right to cancel within three business days.
7. What type of insurance protects against employee job-related
injuries?
A. General liability insurance
B. Workers’ compensation insurance
C. Property insurance
D. Builder’s risk insurance
Correct Answer: B. Workers’ compensation insurance is mandatory to cover
employee injuries.
8. When must a contractor provide a preliminary 20-day notice?
, A. At project completion
B. At the start of providing labor or materials
C. After payment is missed
D. Only on public projects
Correct Answer: B. The 20-day notice preserves the right to file a
mechanic’s lien.
9. What happens if a contractor works without a valid license in
California?
A. Nothing if the job is completed
B. They may face fines and cannot legally collect payment
C. Only a warning is issued
D. License is automatically renewed
Correct Answer: B. Unlicensed contractors face penalties and loss of
payment rights.
10. Which contract price format allows for changes in cost based on
actual expenses?
A. Lump sum
B. Fixed price
C. Cost-plus
D. Unit price
Correct Answer: C. Cost-plus contracts adjust based on actual costs plus a fee.