Florida General Contractor - Certified General
Contractor (CGC) – Contract Administration Exam
ACTUAL EXAM COMPLETE 200 QUESTIONS AND
VERIFIED SOLUTIONS LATEST UPDATE THIS YEAR
Florida Certified General Contractor (CGC) – Contract Administration Exam
Advanced MCQs (Batch 1: 50 Questions | Scenario-Based | With Rationales)
1.
A contractor enters into a lump sum contract but later encounters significant unforeseen site
conditions increasing costs. Which contractual principle determines whether the contractor can
recover additional compensation?
A. Force majeure clause
B. Differing site conditions clause
C. Liquidated damages clause
D. Indemnification clause
Correct Answer: B
Rationale: A differing site conditions clause allows contractors to request compensation when
actual site conditions differ materially from those indicated in the contract.
,Page 2 of 101
2.
During a project, a subcontractor fails to submit a Notice to Owner within the required
timeframe. What is the most likely consequence regarding their payment rights?
A. They can still file a lien anytime
B. They lose lien rights under Florida law
C. They automatically receive payment
D. The owner must still pay them directly
Correct Answer: B
Rationale: Failure to serve a timely Notice to Owner (NTO) results in loss of lien rights under
Florida law.
3.
A contractor submits a bid significantly lower than competitors due to a clerical error in
calculations. After award but before signing, what is the most appropriate action?
A. Proceed with contract at submitted price
B. Withdraw bid citing mistake if proven
C. Demand change order immediately
D. Refuse to perform without penalty
Correct Answer: B
,Page 3 of 101
Rationale: Contractors may withdraw bids due to documented clerical errors, depending on
jurisdiction and timing.
4.
An owner issues a directive requiring additional work without agreeing on price or time
adjustment. What contractual mechanism allows the contractor to proceed while preserving
rights?
A. Addendum
B. Construction change directive
C. Punch list
D. Notice of commencement
Correct Answer: B
Rationale: A construction change directive allows work to proceed before full agreement on
cost/time.
5.
A contractor experiences delays due to unusually severe weather conditions beyond normal
expectations. Which contract provision most directly addresses this situation?
, Page 4 of 101
A. Indemnification clause
B. Force majeure clause
C. Warranty clause
D. Payment bond
Correct Answer: B
Rationale: Force majeure clauses cover unforeseeable events like extreme weather affecting
project timelines.
6.
A project reaches substantial completion, but several minor items remain unfinished. What is
the primary purpose of creating a punch list at this stage?
A. Identify contract price
B. List incomplete or defective items
C. Approve final payment
D. Terminate subcontractors
Correct Answer: B
Rationale: A punch list documents remaining work required before final completion.
7.