In case of discrepancies among the contract documents, which document takes the
highest precedence? - Special Provisions
What two types of Estimates are needed to pay for the work performed by contractors?
- Final & Progress Monthly
Contractors Recieve progress payments on the basis of? - Monthly Progress Estimates
Which of the following sets forth the Department's methods and procedures for
preparing and checking final estimates? - Preparation and Documentation Manual
(PDM)
Which Document contains a series of Specially designed forms that show both original
estimates of quantities and the final quantities as measured ad accepted? -
Computation Books
Which Document contains alignment notes, cross-section notes, linear and area
measurements and dimension sketches? - Field Notebooks
Where are major changes during construction documented and "as-built" conditions
shown? - Field Notebooks
What identification is needed to show on the front cover of a field book? - FEID,
Contract number, General contents of the book
When making corrections to a field book entry, you should: - strike through, initial and
enter correct data and date
What should be started on the first lined page (page 1) of a field book? - INDEX