What makes up a quality asphalt A quality asphalt mixture is determined by the
mixture? constructability, if it conforms to Specifications,
and if it satisfies functional requirements.
CQC contractor quality control
Superpave Asphalt mix design system since 1998
QCP Quality control plan
QCM Quality control Manual
QC Quality Control (Contracting Testing and
Inspection)
VT Verification Testing (FDOT or CEI Verification)
CEI Construction Engineering and Inspection
RT Resolution Testing (FDOT)
, IV Independent Verification Testing
IA Independent Assurance Testing
The decision-making authority on a Needs to be given to the level closet to the work
job needs to be given to who? as specified in the specifications. It ensure a quick
handle on situations and issues.
The governing order of project Special Provisions
documents from high (1) to low (7)
starts with the highest being
The governing order of project Technical Special Provisions
documents from high to low (2)
The governing order of project Plans
documents from high to low (3)
The governing order of project Road design, structures, and traffic operations
documents from high to low (4) standards
The governing order of project Developmental Specifications
documents from high to low (5)
The governing order of project Supplemental Specifications
documents from high to low (6)
The governing order of project Standard Specifications
documents from high to low (7)
|COMPREHENSIVE MOST TESTED (frequently
tested) QUESTIONS AND VERIFIED ANSWERS |
GET IT 100% ACCURATE!!
Save
Terms in this set (94)
What makes up a quality asphalt A quality asphalt mixture is determined by the
mixture? constructability, if it conforms to Specifications,
and if it satisfies functional requirements.
CQC contractor quality control
Superpave Asphalt mix design system since 1998
QCP Quality control plan
QCM Quality control Manual
QC Quality Control (Contracting Testing and
Inspection)
VT Verification Testing (FDOT or CEI Verification)
CEI Construction Engineering and Inspection
RT Resolution Testing (FDOT)
, IV Independent Verification Testing
IA Independent Assurance Testing
The decision-making authority on a Needs to be given to the level closet to the work
job needs to be given to who? as specified in the specifications. It ensure a quick
handle on situations and issues.
The governing order of project Special Provisions
documents from high (1) to low (7)
starts with the highest being
The governing order of project Technical Special Provisions
documents from high to low (2)
The governing order of project Plans
documents from high to low (3)
The governing order of project Road design, structures, and traffic operations
documents from high to low (4) standards
The governing order of project Developmental Specifications
documents from high to low (5)
The governing order of project Supplemental Specifications
documents from high to low (6)
The governing order of project Standard Specifications
documents from high to low (7)