Transmission Operator and Balancing Authority personnel that are responsible for complying with
NERC standards must receive at least five days of training each year that includes which of the
following?
a) Realistic simulations of system emergencies
b) Updates on Market operation
c) Generator bidding methodology
d) Calculating Available Transmission Capacity ✔Correct Answer-a
Each Transmission Operator and Balancing Authority shall have emergency plans that will enable it to
a) Cover all possible contingencies without violating any limits
b) Mitigate operating emergencies
c) Restore the system to normal within 10 minutes
d) Prevent any emergency condition from occurring ✔Correct Answer-b
If studies were being performed to evaluate next-day system conditions, which of the following
information would be the LEAST useful?
a) Projected Transmission outages
b) Generation schedule
c) Load forecast
d) Current day weather forecast ✔Correct Answer-d
When system conditions are such that emergency procedures are expected to be implemented,
which of the following actions should be considered first?
a) Shed firm load
b) Implement Active Load Management
c) Return outaged equipment to service
d) Request a voltage reduction ✔Correct Answer-c
If your system is experiencing a capacity deficiency emergency, which of the following is NOT an
acceptable action?
a) Purchase emergency energy
b) Curtail interchange export
c) Lean on the tie-lines
d) Shed load ✔Correct Answer-c
Why are drastic frequency variations experienced in the early stages of restoration?
a) Lack of load
b) Less generation operating for control
c) System voltages are too high
d) Underfrequency relays are disabled ✔Correct Answer-b