This standard shall apply to ______ intended to carry water for fire service mains
AHJ
Working plans shall be submitted for approval to the _____ before any equipment is installed or
remodeled.
Pressure-Regulating devices
____ shall not be used
Control Valves
______ shall not be installed in the piping from the fire department connection to the fire service main
Control Valves
_____ shall be permitted in the system downstream of the fire department connection
Check Valve
When more than one water supply exists, a ___________ shall be installed in each connection
Control Valve
All check valves shall have a ________ installed upstream and downstream of the check valve.
40 ft
A post indicator valve installed not less than____ from the building
32-40 inches
Where post indicator valves are used, they shall be set so that the top of each post is _______ above
final grade
not be required
Supervision of underground gate valves with roadway boxes shall ____________
not be less than 6 inches
The connection from the hydrant to the main shall ___________
not less than 40 ft
Hydrants shall be located _________ from the buildings to be protected
flat stones, concrete slabs, or other approved material
Hydrants shall be installed on __________
less than 18 inches
1
Revised graded A++ 20206/2027
This standard shall apply to ______ intended to carry water for fire service mains
AHJ
Working plans shall be submitted for approval to the _____ before any equipment is installed or
remodeled.
Pressure-Regulating devices
____ shall not be used
Control Valves
______ shall not be installed in the piping from the fire department connection to the fire service main
Control Valves
_____ shall be permitted in the system downstream of the fire department connection
Check Valve
When more than one water supply exists, a ___________ shall be installed in each connection
Control Valve
All check valves shall have a ________ installed upstream and downstream of the check valve.
40 ft
A post indicator valve installed not less than____ from the building
32-40 inches
Where post indicator valves are used, they shall be set so that the top of each post is _______ above
final grade
not be required
Supervision of underground gate valves with roadway boxes shall ____________
not be less than 6 inches
The connection from the hydrant to the main shall ___________
not less than 40 ft
Hydrants shall be located _________ from the buildings to be protected
flat stones, concrete slabs, or other approved material
Hydrants shall be installed on __________
less than 18 inches
1