Correct Answers| Graded A+
What do you call a person authorized to represent another (the principal) in some capacity? He/she can
only act
within this capacity or "scope of authority" to bind the principal.
A. Engineer
B. Alternate
C. Project Manager
D. Agent - correct answers Answer: D
Budgeted cost of work scheduled is all of the following except:
A. Total costs incurred in accomplishing work in a given-time period
B. Baseline for performance measurement
C. Sum of the budgets for work scheduled
D. Includes portion of the budget for level-of-effort work - correct answers Answer: D
Which of the following is NOT an aspect of quality management?
A. Quality assurance
B. Quality planning
C. Quality checking
D. Quality control - correct answers Answer: C
Cost performance index (CPI) is defined by AACE International as: (assume no change in
budgeted quantities)
,A. ACWP/BCWS
B. BCWS/BCWP
C. ACWP/BCWP
D. BCWP/ACWP - correct answers Answer: D
____________ is the application of total resources ($-workers-supports) and activity durations of the
logic
diagram.
A. Planning
B. Forecasting
C. Scheduling
D. Modeling - correct answers Answer: C
____________is defined as the earned work hours or dollars for all accounts divided by the budgeted
work
hours or dollars for all accounts.
A. Percent complete
B. Cost to complete
C. Earned value
D. Forecast - correct answers Answer: A
_____________is defined as the budget for the cost (work) account times the percent complete for that
account.
A. Percent complete
B. Forecast
C. Cost to complete
,D. Earned value - correct answers Answer: D
____________ is defined as covering work whose component activities are less defined and whose
interrelationships are conditional.
A. Soft logic
B. Hard logic
C. Deductive logic
D. Inductive logic - correct answers Answer: A
A work breakdown structure (WBS) is developed because:
A. It avoids omissions of key product activities through a systematic planning process; removes the
complexity
of the project by dividing it into manageable units; and provides a framework.
B. It defines specific tasks within a project from which schedules can be developed; it aids in linking
activities
with resources; it facilitates communication; and it allows integration of project plans
C. It can be illustrated by individual bars for major phases, such as permitting, funding, engineering,
procurement construction, commission/startup
D. It can be illustrated by a simple bar, with important milestones represented by symbols at the
planned time of
occurrence - correct answers Answer: B
If a project is said to be on a "fast track program/' the fast track method is:
A. Simultaneous working engineering, procurement, and construction, with appropriate overlap from
each
phase of work so that delays are eliminated and all the work is streamlined into a correct plan of
logic/sequence
and duration for all of the work
, B. First completing engineering and procurement, then executing construction
C. Analyzing the project and specifying the basic approach to be used in its execution; segmenting the
project
into reasonable number of activities; estimating the time required to perform each activity; placing the
activities
in time order, considering both sequential and parallel performance
D. Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the
durations
in the n p schedule that have been based on assumptions regarding the \hay the work would be
performed;
revise th - correct answers Answer: A
Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or
task
shown on the schedule, is:
A. Activity ID
B. WBS Code
C. Resource
D. Account number - correct answers Answer: A
The process of stating goals and determining the most effective way of reaching them is the definition
for:
A. Implementing
B. Mission Statement
C. Managing
D. Planning - correct answers Answer: D
A schedule's late dates are calculated during the: