Project Planning (definition) Identifying all activities necessary to successfully
complete the project
Work Breakdown Structure A hierarchical breakdown of the project into
(definition) deliverables and work packages
Purpose of a WBS Defines work, identifies needed expertise,
supports scheduling and cost control
https://quizlet.com/1158855913/cpm-exam-2-exam-most-tested-questions-and-verified-solutionsget-it-100-accurate-2026-flash-cards/?new 1/5
, 3/22/26, 5:35 PM CPM Exam 2 EXAM, MOST TESTED QUESTIONS AND VERIFIED SOLUTIONS/GET IT 100% ACCURATE!! 2026!! Flashcards | …
How a WBS is organized Product-oriented family tree (deliverables →
subdeliverables → work packages)
Work package (definition) Smallest WBS element where time and cost can be
accurately estimated
Uses of a work package Defines scope, identifies resource needs,
communicates assignments
Scheduling (definition) Determining sequence, duration, and start/finish
dates of activities
Planning vs Scheduling Planning = what to do; Scheduling = when and in
what order it is done
Uses of project schedules Forecast resources, track progress, communication,
claims documentation
Bar (Gantt) chart definition Activities shown as bars across a time scale
Bar (Gantt) chart — Pros Easy to read, good for overall project planning
Bar (Gantt) chart — Cons Does not show logic relationships, difficult to
update
Critical Path Method (CPM) A scheduling method that identifies the critical path
of activities
CPM — Pros Shows logic relationships, identifies critical path,
easy to update
CPM — Cons Can be complex and harder to read