FAR 17.106-3(g) authorizes the head of the contracting activity (HCA) to approve the
use of variable unit prices under multi-year contract procedures. Can the HCA's
authority be delegated to the chief of the contracting office?
Yes
No
Not enough information - correct answer Yes
You are a contracting officer contemplating award of a $1,000,000 contract for other
than commercial services to be performed in Singapore. The period of performance is
one year. Is the contractor required to comply with the policy at FAR 23.504(c)?
,Yes
The 30 day requirement may be extended if the contracting officer agrees in writing
that circumstances warrant a longer period of time to comply.
No - correct answer No
Who can sign a determination and findings justifying the use of a $30M cost-plus-
award fee contract for a DOD requirement?
Only the head of the contracting activity (HCA)
The HCA or designee no more than one level below the HCA
An individual one level above the contracting officer
The contracting officer - correct answer The HCA or designee no more than one level
below the HCA
, Which statement is true regarding the suspension of contractors?
Suspension decisions always apply to all divisions or other organizational elements of
the contractor without exception
A contractor's suspension is generally effective throughout the executive branch of the
government
If a cause for suspension exists, the government must always suspend the contract -
correct answer A contractor's suspension is generally effective throughout the
executive branch of the government.
Which statement is correct regarding the assignment of claims for a DOD $300,000
nonpersonal services contract?
The assignment of claims may be prohibited for this contract
The assignment of claims may not be prohibited for this contract