Two factors cause construction industry to become highly
specialized - Answer-changing markets and increased
tech and regulations
Factor that will influence both government and
construction industry in the future - Answer-New
government regulations, greater influence from consumer,
improvement in QC and QA requirements, construction-
oriented management info systems, formal partnering
involving stakeholders, more reliance on design-build,
more considerate for live cycle requirements and
increased based incentives
A definable feature of work: - Answer-Can consist of a
combination of multiple specification sections depending
upon the nature of the work
Actual construction on the jobsite begins: - Answer-After
an interim or final QC is accepted
,2|Page
All submittals for government approval must be provided
by the _________________ in time to allow for the review,
approval, procurement, delivery, and performance of
preparatory phase for an item before it is needed for
construction. - Answer-Contractor to the Government
An effective contractor quality control program will -
Answer-Be an incentive for work to be done correctly the
first time resulting in earlier completion, reduced field
overhead costs, and greater profits
Characteristics that describe a definable feature of work
include: - Answer-Cross-referenced listings to the
contractor's construction schedule that may have more
than one definable feature under a section of the
specifications
Construction Quality Management is the performance of
tasks, which ensure that construction is performed: -
Answer-According to plans and specifications, on time,
within a defined budget and a safe work environment
, 3|Page
Contractor testing procedures: - Answer-are outlined in the
Quality Control Plan as defined by section 0145N/01451A
and addressed at the Coordination and Mutal
Understanding Meeting (Navy).
Control is - Answer-A continual system of planned future
activities (its preventative)
Design-Build contracts require - Answer-The QC Manager
to be in place and take an active role in the review and
coordination of the design.
During the punch-out inspection of a project: - Answer-The
contractor prepares a punch list and makes corrections
A cumulative list of job deficiencies/rework items can be
found in: - Answer-Quality Control Report
Contractor benefits of CQM - Answer-Increased profit and
production, better communications, planning, improved
organizational skills, and outstanding performance
evaluations to obtain future contracts.