Quality control focuses on ______. - Answer-Meeting the
specific quality requirements required in the contract
documents
What is the required level tolerance specified by most
manufactures for setting a crane? - Answer-1%
You are setting a rooftop air handler. The top of the roof
parapet is 60-ft above the finish grade that the crane is
sitting on. The rigging from the end of the boom is 5 ft from
the end of the boom and includes the hook. The air
handler and the slings to lift it are 10 ft. high. The minimum
distance from the building that you can set the crane is 45
ft. The air handler is to be set 40 ft from the edge of the
roof. What minimum (calculated) length of boom will you
need, and how far from the building will you set the crane?
- Answer-142 ft and 60 ft ?
,2|Page
If the projected lift exceeds 75% of the crane's rated
capacity, or if there are multiple cranes used for a lift, it is
considered a "critical lift". - Answer-True
What is the average time to erect and dismantle a 165 ft
tower crane? - Answer-21 days
In selecting a crane, you need to consider the weight of
the load (crane attachments, wire rope, slings, and block),
maximum radius of swing to lift the load, and the
combined height of the load, slings, block, and vertical lift.
- Answer-True
If you are willing to accept no more than a 20% chance of
exceeding the design capacity of the drainage culvert for
your project, what rainfall intensity factor would...
(incomplete, graph question) - Answer-1.18
Key principles to erosion control include _________.
(Select all that apply) - Answer-Minimize disturbed area
and protect natural features and soil
, 3|Page
Control of stormwater flowing onto and through the project
site
Protection of slopes
When must the application (notice of intent) be made for
obtaining permit coverage for the construction site? -
Answer-No later than 14 days prior to the start of
construction ?
What federal regulation governs the development of
SWPPP? - Answer-NPDES
To determine the fleet size (number of haulers) for the
project, one of two deterministic models are used. What
are the two models? - Answer-rational and queues
The CQM process provides full documentation of the
materials incorporated into the work, work performed, and
tests results of work in place. - Answer-True
Within the federal CQM (construction quality
management) program, who has the responsibility for
quality control? - Answer-Builder