Relative to stormwater permitting, all of the following must
occur before construction starts except
-prepare the SWPPP
-determine the operator(s)
-submit the notice of intent (NOI)
-submit the notice of termination (NOT) - Answer-submit
the notice of termination (NOT)
The stormwater notice of intent (NOI) must be submitted
-after the sediment discharge
-after the SWPPP is prepared and before starting
construction
-after stormwater BMPs have been installed
- after stormwater inspectors issue a violation - Answer-
after the SWPPP is prepared and before starting
construction
,2|Page
Potential pollutant source stored on a construction site
may include
-petroleum storage tanks
-soil amendments
-masonry materials
-all of the above - Answer-all of the above
The SWPPP implementation sequence may be modified
-as the qualified inspector deems necessary
-after consulting with the project SWPPP designer (CEC)
and, if required, the project owner and receiving written
approval
-it you experience a rain event on your project site
-after discussing runoff problems with your BMP installer -
Answer-after consulting with the project SWPPP designer
(CEC) and, if required, the project owner and receiving
written approval
A SWPPP site map will show all of the following except
-locations of BMPs
-Notices of Violation
-phasing and sequences
, 3|Page
-limits of disturbance - Answer-Notices of Violation
Which of the following information is to be posted at the
entrance to the site?
-construction site notice
-permit authorization
-location of the SWPPP
-all of the above - Answer-all of the above
The 1970's law that set into place the regulation of
stormwater is:
-the federal pollution discharge elimination rule
-the stormwater pollution control act
-the national water control act
-the clean water act - Answer-the clean water act
Requirements for managing stormwater activity on a
construction site are outlined in the following regulation
-NOI
-NPDES
-NOT
-DOT - Answer-NPDES