Which of the following is not an option through the Contact
Manager? - Answer-Users
You can data transfer an estimate via XactAnalysis to
another Xactimate user without knowing their XactNet
address. - Answer-False
The only way to update your Xactimate version is through
a disc. - Answer-False
The ability to merge data already saved from your contact
manager directly into an estimate does not
exist. - Answer-False
Xactimate can be viewed in English and printed in a
different language - Answer-True
,2|Page
Which of the following is not an option from the Project
tab? - Answer-Complete a sketch within the project
Which of the following is not a wall type option for stairs? -
Answer-Missing below stairs
The loss recap automatically updates from an estimate. -
Answer-true
When using the Custom staircase tool, after clicking once,
the RED measurement indicates what? - Answer-The total
rise of the staircase
This tool allows you to change the direction that the sloped
or peaked ceiling is running? - Answer-Orientation
When adding a new level, how many feet will sketch add
or subtract from the previous level? - Answer-9
When working on multiple estimates in the same
city/state/zip, you can set up Project Loss Defaults for that
city/state/zip to save time. - Answer-True
, 3|Page
Where in Xactimate can you go to change the default wall
thickness for all future estimates? - Answer-Control
Center/Preferences
This is a shortcut used in Model Statements to pre-fill data
that has already been recorded in an estimate. - Answer-
Token
In Sketch, the keyboard shortcut for resetting your visible
windows is CTRL + SHIFT + R. - Answer-True
There is no way to re-organize the members of the
Grouping pane in Estimate Items - Answer-False
Which of the following are Roof Variables - Answer-SF,
SQ, HIP, VAL, R, P
An alternate method of estimating for a loss can be done
from the Sketch Tab. - Answer-True
Draw lines to match the following Staircase Variable to its
correct definition - Answer-a. Tread Count TCAS