Temporary stabilization should be implemented -
ANSWER-Immediately on all disturbed areas that are
likely to or will remain inactive for 14-days or more.
The primary purpose of a construction exit is to -
ANSWER-Remove sediment from construction site
vehicles and minimize track out.
,Common types of erosion include - ANSWER-Gully,
Sheet, and Rill.
Proper spill management should include all of the
following EXCEPT:
1. Fully stocked spill kits
2. Proper location and signage for spill kits
3. Proper landing and disposal of contaminated material
4. Installation of a spill pit on your construction sites -
ANSWER-4. Installation of a spill pit on your construction
sites.
, The best location for portable toilets on your construction
site is - ANSWER-On level ground, in low construction
traffic areas.
The following must be marked on Site Maps in the jobsite
trailer as works progress - ANSWER-The dates when BMP
changes or additions take place.
While inspecting field BMPs, the SWPPP Inspector should
perform all of the following EXCEPT:
1. Note BMPs in need of repair or maintenance
2. Verify BMPs are installed per plans and specifications
3. Assume BMPs are in good condition from a distance