While inspecting field BMPs, the SWPPP inspector should perform all of the
following EXCEPT: - CORRECT ANSWER-Assume BMPs are in good condition
from a distance
If your site is inspected by US EPA, or another regulatory agency, you should: -
CORRECT ANSWER-Be Courteous, Attend their inspection, Allow access to site
and documentation -- All of the above
The stormwater Notice of Intent (NOI) must be submitted - CORRECT
ANSWER-After the SWPPP is prepared and before starting construction
Potential pollutant sources stored on a construction site may include - CORRECT
ANSWER-Petroleum storage tanks, soil amendments, masonry materials -- all of
the above
, The SWPPP implementation sequence may be modified - CORRECT ANSWER-
After consulting with the project SWPPP designer (CEC) and if required the Project
Engineer
A SWPPP Site Map will show all of the following except - CORRECT ANSWER-
Notices of Violation
Which of the following information is to be posted at the entrance to the site? -
CORRECT ANSWER-Construction Site Notice, Permit authorization, Location of
the SWPPP -- All of the above
The 1970's law that set into place the regulation of stormwater is: - CORRECT
ANSWER-The Clean Water Act
Requirements for managing stormwater activity on a construction site are
outlined in the following regulation: - CORRECT ANSWER-NPDES
Which of the following is never an allowable stormwater discharge from a
construction site? - CORRECT ANSWER-Discharge from contaminated
groundwater