CMIT 2026 EXAM COMPLETE (200) CURRENT
TESTING QUESTIONS AND DETAILED
CORRECT ANSWERS|GUARANTEED PASS.
CMIT
Prepare for the CMIT Exam with this concise study resource
covering construction management principles, project
coordination, safety standards, and exam-style questions. It
reinforces key concepts aligned with certification standards
from the Construction Management Association of America.
Suitable for individuals pursuing the Certified Manager-in-
Training credential in construction management.
It is NOT the purpose of the General Conditions to:
A) Clearly define the owner and contractor rights and
responsibilities.
B) Provide a procedure for executing changes in the work
scope in a fair and equitable manner.
C) Provide a detailed scope of work.
D) Clearly define the roles and responsibilities of the CM ✓
✓ ...... ANSWER ....... C) Provide a detailed scope of
work.
, Page 2 of 60
The CM has the authority on behalf of the owner to
disapprove or reject work and to revoke, alter, enlarge or
relax any requirements of the contract documents.
True False ✓ ✓ ...... ANSWER ....... False
The owner at any time and without cause may suspend the
work for a period of 180 days by a notice in writing to the
contractor.
True False ✓ ✓ ...... ANSWER ....... True
The owner has an obligation to exercise its right to stop work
when it would be to the benefit of the contractor.
True False ✓ ✓ ...... ANSWER ....... False
If the contractor fails to proceed to correct defective work in
a timely fashion, the owner has the right to access the work
and/or to do the corrective work itself.
True False ✓ ✓ ...... ANSWER ....... True
All communications to the designer and owner from the
contractor must be submitted through the CM.
, Page 3 of 60
True False ✓ ✓ ...... ANSWER ....... True
Under the CMAA contract document A-3, General
Conditions for Agency CM, the contract documents order of
precedence clause places the "General Conditions" as the
highest order of precedence document.
True False ✓ ✓ ...... ANSWER ....... False
The contractor shall rely upon the accuracy or factual data
contained in the reports of exploration and tests of surface
and sub-surface conditions at the site or contiguous to the
site that were used by the designer in preparing the contract
documents.
True False ✓ ✓ ...... ANSWER ....... True
The contractor's duty and responsibility for safety and
protection of the work extends until a final inspection is
conducted.
True False ✓ ✓ ...... ANSWER ....... True
The CM can require removal of a contractor or subcontractor
employee with whom the CM deems objectionable.
, Page 4 of 60
True False ✓ ✓ ...... ANSWER ....... True
The contractor has no obligation to provide other contractors
working on the site safe access to the site.
True False ✓ ✓ ...... ANSWER ....... False
If the contractor causes damage to the work property of
another contractor working on site, the contractor shall seek
to remedy the situation by changing the contractor's scope
of work.
True False ✓ ✓ ...... ANSWER ....... False
The CM must approve the scheduling system proposed by
the contractor prior to the contractor preparing the
construction schedule.
True False ✓ ✓ ...... ANSWER ....... True
If it becomes apparent that the contractor's schedule will
not be met and it is due to the fault of the contractor, the
contractor must agree to increase the number of employees
to regain the lost schedule progress, and submit a recovery
schedule.