What does the MDA and/or CAE and the requirements leadership ensure during
CDD-V?
Give this one a try later!
Validated requirements continue to address the priorities of the users in a
cost effective & affordable way
What are the requirements to go for MS-B approval?
Give this one a try later!
, - Demonstration that all sources of risk have been adequately mitigated
- Full funding in the FYDP
- Compliance with affordability goals
- Framing assumptions
What phase is after MS-A?
Give this one a try later!
Technology Maturation and Risk Reduction
What is the purpose of the TMRR Phase?
Give this one a try later!
- Reduce Technology, Engineering, Integration, and Life Cycle Cost Risks
- Demonstrate Critical Technologies on Prototypes
- Complete Preliminary Design
When should an Affordability Analysis happen?
Give this one a try later!
Before each milestone
What is the CSB Configurations Steering Boards role in CDD-V?
CDD-V?
Give this one a try later!
Validated requirements continue to address the priorities of the users in a
cost effective & affordable way
What are the requirements to go for MS-B approval?
Give this one a try later!
, - Demonstration that all sources of risk have been adequately mitigated
- Full funding in the FYDP
- Compliance with affordability goals
- Framing assumptions
What phase is after MS-A?
Give this one a try later!
Technology Maturation and Risk Reduction
What is the purpose of the TMRR Phase?
Give this one a try later!
- Reduce Technology, Engineering, Integration, and Life Cycle Cost Risks
- Demonstrate Critical Technologies on Prototypes
- Complete Preliminary Design
When should an Affordability Analysis happen?
Give this one a try later!
Before each milestone
What is the CSB Configurations Steering Boards role in CDD-V?