Where should you create an RFI so that it is automatically linked to the correct location
on the project's drawings? - correct answer Drawings Tool
Which field is used to allow a user to add a response to the RFI? - correct answer
Assignee
True or False: You can only link a drawing to a "Draft" RFI. - correct answer False
Mark all that apply: When viewing an RFI, what information are you able to view? -
correct answer Copies of all related emails
The original RFI question
Related Items
,The designated "official response(s)"
Which view should you use if you want to view photos in chronological order based on
when they were taken? - correct answer Timeline
If you don't select an album when uploading photos where will the photos will be
uploaded? - correct answer "Unclassified" Album
What is the easiest way to keep track of project progress photos? - correct answer
Add yourself and any relevant team members as subscribers to the Photos tool
What is the best way to call someone's attention to a specific photo? - correct answer
@mention them on the photo in the Comments section
, What is the best way to find out which actions you can perform offline on your mobile
device? - correct answer Go to https://support.procore.com and view the Mobile
Permissions Matrix
What permission level will you need to create new meetings and view all of the
meetings in the project, even if they're marked private? - correct answer Admin
When you see a text field in Procore that has a blue caret in the top right corner of the
cell, what does it mean? - correct answer The field can be edited
Who can view meetings that are marked as private? (Mark all that apply) - correct
answer Scheduled attendees
Distribution list members
The creator of the meeting
Users with 'Admin' permissions on the Meetings tool