An activity is coded as 0793-31 62 13.16 using the Construction
Specifications Institute's MasterFormat 2012. THis coding represents
(A) clearing and grubbing land
(B) demolition of an existing structure
(C) shoring an excavation
(D) driving a deep foundation pile - Ans(D) driving a deep foundation pile
For which of the following is the Program Evaluation and Review
Technique (PERT) NOT used?
(A) construction projects
(B) computer programming assignments
(C) preparation of bids and proposals
(D) queueing problems - Ans(D) queueing problems
In addition to protective goggles, what personal protective equipment is
required when welding pipe in a deep trench?
(A) fall protection harness