CQM C COMPREHENSIVE TEST 2026 QUESTIONS ANSWERS
CERTIFIED STUDY GUIDE A+
>Design-Build contracts require: . Answer. *The QC Manager to be in place and
take an active role in the review and coordination of the design*
>Which of the following is included in all three phases of the Three Phases of
Control . Answer. Safety
>The purpose of Construction Quality Management is to . Answer. *Achieve the
quality established by properly developed requirements through the combined
responsibility, but separate, efforts of contractor and Government personnel*
>Testing is extremely important in Construction Quality Management and is
performed by . Answer. Both the contractor and the Government
>The primary purpose of the Three-Phase Control System is to: . Answer. Require
the contractor to plan, schedule, and perform quality management actions to
assure work meets all specified quality standards
>Quality Assurance Personnel have the responsibility to: . Answer. *require the
contractor to maintain the quality specified in the plans and specifications*
>the ____ is the appropriate time to assure that all materials and/or equipment
have been tested. submitted, and approved. . Answer. Preparatory Phase
>The Preconstruction Conference and the Coordination and Mutual
Understanding Meeting are: . Answer. conducted prior to the commencement of
any physical construction work
, >Contractor testing procedures: . Answer. are specified in the technical
specifications, outlined in the Quality Control Plan, and addressed at the
Coordination and Mutual Understanding Meeting.
>The Quality Control Plan contains: . Answer. Identification of individual quality
control personnel, including name, qualifications, assigned duties, responsibilities
and authorities
>Tests that are unnanounced, randomly performed, and repeat quality control
tests are: . Answer. quality assurance tests
>The contractor is required to conduct a preparatory phase meeting before they
begins any definable feature of work except when: . Answer. there are no
exceptions to the rule
>During the punch-out inspection of a project: . Answer. *Quality control
personnel prepare a punch-list and make corrections*
>The Quality Control Report should include: . Answer. All of the above :
Work in Progress
Work that has been completed
Problem areas
>In a design-build contract, if the contractor has a question about the design,
what is the process to get an answer? . Answer. *Contractor submits a design
verification request to the contractor's design team.*
CERTIFIED STUDY GUIDE A+
>Design-Build contracts require: . Answer. *The QC Manager to be in place and
take an active role in the review and coordination of the design*
>Which of the following is included in all three phases of the Three Phases of
Control . Answer. Safety
>The purpose of Construction Quality Management is to . Answer. *Achieve the
quality established by properly developed requirements through the combined
responsibility, but separate, efforts of contractor and Government personnel*
>Testing is extremely important in Construction Quality Management and is
performed by . Answer. Both the contractor and the Government
>The primary purpose of the Three-Phase Control System is to: . Answer. Require
the contractor to plan, schedule, and perform quality management actions to
assure work meets all specified quality standards
>Quality Assurance Personnel have the responsibility to: . Answer. *require the
contractor to maintain the quality specified in the plans and specifications*
>the ____ is the appropriate time to assure that all materials and/or equipment
have been tested. submitted, and approved. . Answer. Preparatory Phase
>The Preconstruction Conference and the Coordination and Mutual
Understanding Meeting are: . Answer. conducted prior to the commencement of
any physical construction work
, >Contractor testing procedures: . Answer. are specified in the technical
specifications, outlined in the Quality Control Plan, and addressed at the
Coordination and Mutual Understanding Meeting.
>The Quality Control Plan contains: . Answer. Identification of individual quality
control personnel, including name, qualifications, assigned duties, responsibilities
and authorities
>Tests that are unnanounced, randomly performed, and repeat quality control
tests are: . Answer. quality assurance tests
>The contractor is required to conduct a preparatory phase meeting before they
begins any definable feature of work except when: . Answer. there are no
exceptions to the rule
>During the punch-out inspection of a project: . Answer. *Quality control
personnel prepare a punch-list and make corrections*
>The Quality Control Report should include: . Answer. All of the above :
Work in Progress
Work that has been completed
Problem areas
>In a design-build contract, if the contractor has a question about the design,
what is the process to get an answer? . Answer. *Contractor submits a design
verification request to the contractor's design team.*