Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CON 3900V Mastery: The Ultimate FAR Exam Cram Kit – 150+ Verified Q&A

Beoordeling
-
Verkocht
-
Pagina's
76
Cijfer
A+
Geüpload op
26-03-2026
Geschreven in
2025/2026

Ace your CON 3900V final with confidence! This comprehensive practice exam bank features over 150 meticulously crafted questions with detailed, verified answers directly from the FAR. Covering everything from contract types and quality assurance to source selection and terminations, this is your all-in-one resource to master complex acquisition concepts and pass the first time.

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

1|Page




CON 3900V Practice Exam TEST FINAL EXAM AND PRACTICE
EXAM 20262027 BANK 2 VERSIONS QUESTIONS WITH
DETAILED VERIFIED ANSWERS EXAM QUESTIONS WILL
COME FROM HERE (100% CORRECT ANSWERS A+ GRADED




1. Contractors are responsible for:


A. Appointing Government Contracting Officer Representatives
B. Managing Government quality control
C. Tendering to the Government for acceptance only those supplies or
services that conform to contract quality requirements
D. Prescribing Government quality assurance - ANSWER--C. Tendering
to the Government for acceptance only those supplies or services that
conform to contract quality requirements


2. During discussions, the contracting officer:
A. Should discuss aspects of an offeror's proposal if alterations or
explanations would enhance the proposal's potential for award
B. Must pursue obtaining what is best for the Government value
irrespective of the evaluation factors set forth in the solicitation
C. May not negotiate with offerors for increased performance beyond
mandatory minimums

,2|Page


D. May favor one offeror over another during discussions - ANSWER--A.
Should discuss aspects of an offeror's proposal if alterations or
explanations would enhance the proposal's potential for award


Feedback: See FAR 15.306(d)


3. Quality assurance on contract actions valued below the simplified
acquisition threshold (SAT) is:


A. Minimal, unless a special circumstance exists
B. The same as above the SAT
C. More stringent for commercial items
D. Not necessary, as risk of loss is considered too low to justify the
expense - ANSWER--A. Minimal, unless a special circumstance exists


Feedback: See FAR 46.404


4. You have a requirement for an online subscription to Engineering
News Record. The site owner requires payment before they will provide
the license code number to activate the annual subscription. Which
payment form is required?


A. An invoice payment
B. A progress payment

,3|Page


C. A commercial payment
D. An advance payment - ANSWER--D. An advance payment


Feedback: See FAR 32.102(a)


5. Which FAR part is the best source of information regarding
competition requirements?


A. FAR part 1
B. FAR part 6
C. FAR part 7
D. FAR part 13 - ANSWER--B. FAR part 6


Feedback: See FAR 6.000


6. With limited exceptions as authorized by agency regulations, what
does the FAR say about Government employees soliciting and accepting
gifts from contractors? Government employees:


A. May solicit and accept gifts if in accordance with commercial
business practices
B. May solicit and accept gifts in overseas countries where bribery is
legal

, 4|Page


C. May not solicit or accept gifts
D. May not solicit gifts, but may accept gifts if their performance
exceeded standards - ANSWER--C. May not solicit or accept gifts


7. You are a contracting officer who has a $260,000 commercial
contract. You decide you need to terminate the contract because the
contractor has failed to perform. What is the name of this type of
termination?


A. For Noncompliance
B. For Cause
C. For Default
D. For Failure - ANSWER--B. For Cause


Feedback: See FAR 12.403(a)


8. Simplified Acquisition Procedures (SAP) should:


A. Promote competition to the maximum extent practicable
B. Consider all quotations or offers, regardless of the time they are
received, if they are the most reasonable
C. Promote the use of current vendors for time-saving purposes
D. Equally consider all businesses, large or small - ANSWER--A. Promote
competition to the maximum extent practicable

Geschreven voor

Vak

Documentinformatie

Geüpload op
26 maart 2026
Aantal pagina's
76
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$26.34
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
blisslaw4

Maak kennis met de verkoper

Seller avatar
blisslaw4 teach me2
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
-
Lid sinds
1 maand
Aantal volgers
0
Documenten
409
Laatst verkocht
-

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen