Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

BSOP 429 Week 8 Final Exam (Version 2) Questions And Best Explained Latest And Complete (VERIFIED)

Beoordeling
-
Verkocht
-
Pagina's
13
Cijfer
A+
Geüpload op
26-04-2021
Geschreven in
2020/2021

BSOP 429 Week 8 Final Exam (Version 2) BSOP 429 Week 8 Final Exam (Version 2) Questions And Best Explained Latest And Complete (VERIFIED) (TCO 4) The two different approaches to load work centers in job-shop scheduling are (TCO 2) The priority rule where jobs are processed according to the smallest ratio of due date to processing time is (TCO 2) A scheduling rule used for sequencing jobs through two work centers is (TCO 3) The owner and operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:……If he uses the first-come, first-served (FCFS) priority rule to schedule these jobs, what will be the average completion time? (TCO 5) The ultimate goal of JIT operations is to have (TCO 6) Building up an inventory of standard parts or modules instead of immediately producing the finished end items is the essence.. (TCO 7) A kanban card is used to signal that (TCO 10) The type of processing system that is used for highly standardized products is Page 2 (TCO 8) Does cellular manufacturing apply best to repetitive, high-volume product or nonrepetitive, low-volume product? Explain and give an example. (TCO 11) Validate or invalidate the statement that although inventories are maintained, the goal of lean operations is to maintain a minimum of safety stock. (TCO 9) Elaborate on the statement: “The output of the system cannot exceed the output of the bottleneck operation(s).” (TCO 4) Differentiate between infinite loading and finite loading as two major approaches used to load work centers. (TCO 12) Explain why batch process helps maximize worker efficiency. (TCO 2) Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):…………What is the schedule sequence using the first-come, first-served (FCFS) priority rule? (TCO 10) Respond to the question: “Which is better, MRP or JIT?” (TCO 1) The design of the MPC system is influenced by some key features of market demand and product design. Name the key features that will lead to a make-to-stock system and explain the rationale. (TCO 6) Market requirements drive the choice of the shop floor system approach. Describe and explain the type of market requirements that would be suitable for an MRP-based system, along the lines of product design, product variety, and product volume per period, product mix changes, and delivery schedule changes. (TCO 10) Manufacturing strategy also drives the choice of shop floor system. Describe and explain the strategies that lend themselves to a JIT-based system, from the perspective of WIP, changeover cost, and process choice

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

BSOP 429 Week 8 Final Exam

1. (TCO 4) The two different approaches to load work centers in job-shop scheduling are
(Points : 5)
load charts & schedule charts.
Gantt charts & assignment method.
infinite loading & finite loading.
linear programming & makespan.
None of the above

2. (TCO 2) The priority rule where jobs are processed according to the smallest ratio of due
date to processing time is (Points : 5)
CR.
EEDD.
FCFS.
S/O.
SPT.

3. (TCO 2) A scheduling rule used for sequencing jobs through two work centers is (Points : 5)
the critical ratio rule.
the Johnson's rule.
the slack per operation rule.
the shortest processing time rule.
the Pareto rule.

4. (TCO 3) The owner & operator of the local franchise of Handyman, Inc., has four jobs to do
today, shown in the order they were received:

Job Processing Time (hrs) Due (hrs from now)
-------------------------------------------------------------------------------------------------
W44
X35
Y22
Z11


If he uses the first-come, first-served (FCFS) priority rule to schedule these jobs, what will be
the average completion time? (Points : 5)
7.5 hours
5 hours
3 hours
2.5 hours

, 2 hours

5. (TCO 5) The ultimate goal of JIT operations is to have (Points : 5)
no in-process inventories.
cross-trained workers capable of handling every process.
a smooth, rapid flow of materials through the system.
no setup times.
All of the above

6. (TCO 6) Building up an inventory of standard parts or modules instead of immediately
producing the finished end items is the essence of (Points : 5)
delayed differentiation.
kanban.
autonomation.
andon.
matrix management.


7. (TCO 7) A kanban card is used to signal that (Points : 5)
work is needed at the work center.
work is ready to be moved to the next station.
a worker has run out of parts needed for further processing.
a machine has broken down & needs immediate attention.
a machine is ready for preventive maintenance.


8. (TCO 10) The type of processing system that is used for highly standardized products is
(Points : 5)
continuous.
intermittent.
project.
batch.
unit.


1. (TCO 8) Does cellular manufacturing apply best to repetitive, high-volume product or nonrepetitive,
low-volume product? Explain & give an example. (Points : 25)

Geschreven voor

Vak

Documentinformatie

Geüpload op
26 april 2021
Aantal pagina's
13
Geschreven in
2020/2021
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$15.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
HIGHSCORE Masters
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1511
Lid sinds
6 jaar
Aantal volgers
1280
Documenten
2038
Laatst verkocht
2 maanden geleden

3.8

264 beoordelingen

5
129
4
57
3
23
2
18
1
37

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen