and Correct Detailed Answers Already
Graded A+
What elements of RUSLE are independent of location?
a. K
b. R
c. LS
d. C & P - CORRECT ANSWER-D
What does the "P" stand for in the Revised Universal Soil Loss Equation (RUSLE)?
a. Soil erodibility factor
b. Management operations and support practices (sediment controls)
c. Rainfall-runoff erosivity factor
d. Length-slope factor
e. Cover factor (erosion controls) - CORRECT ANSWER-B
What is the difference of an LUP project in comparison to traditional projects?
a. Erosion control is not needed.
b. "Run-On/Run-Off" is not an objective.
,c. Sampling is not required. - CORRECT ANSWER-B
TRUE OR FALSE: The SWPPP is a "living document" that is amended/updated to
reflect conditions & reduce pollutants - CORRECT ANSWER-True
Stockpiles require a linear sediment barrier at all times, and must be covered
prior to a rain event or when inactive. A stockpile is inactive after __days of
inactivity.
a. 3
b. 7
c. 10
d. 14 - CORRECT ANSWER-D
When does the CGP apply? - CORRECT ANSWER-Any construction or
demolition of one acre or more
Activities under the CGP include:
a. Routine maintenance to maintain original line and grade, hydraulic capacity, or
original purpose of the facility.
b. Disturbances to land surfaces solely related to agricultural operations.
, c. Clearing and grading 2 acres of land
d. Discharges of storm water from areas on tribal lands. - CORRECT ANSWER-C
TRUE OR FALSE: if construction of an LUP will occur across several properties, the
utility company, municipality, or other public/private company/agency that owns
or operates the LUP project is responsible for obtaining coverage - CORRECT
ANSWER-True
Risk Level 2 monitoring requirements include:
a. Effluent sampling where applicable
b. Sampling for pH and turbidity
c. Sampling for pH, turbidity, and suspended sediments - CORRECT ANSWER-B
All NAL data must be uploaded within ___ after NAL exceedance has been
identified
a. 24 hours
b. 1 week
c. 10 days
d. 2 weeks - CORRECT ANSWER-C