REVIWED FROM ACTUAL TEST 100 QUESTIONS AND 100%
VERIFIED ANSWERS| A+ GRADE Q&A | INSTANT DOWNLOAD PDF
PMP Certification Practice Exam 2026 – Table of
Contents
1. Project Integration Management
2. Project Scope Management
3. Project Schedule Management
4. Project Cost Management
5. Project Quality Management
6. Project Resource Management
7. Project Communications Management
8. Project Risk Management
9. Project Procurement Management
10.Project Stakeholder Management
1. Project Integration Management
1. What is the primary purpose of a project charter?
It formally authorizes a project, granting the project manager authority to apply
organizational resources to project activities.
2. When should the project management plan be updated?
It should be updated whenever changes occur that affect the project execution, monitoring, or
control, ensuring alignment with project objectives.
3. How does the project manager integrate change requests?
Change requests are reviewed, approved, and incorporated into the project management plan
through the integrated change control process.
4. What is the difference between a project and a program?
A project is a temporary endeavor to create a unique product, service, or result, whereas a
program is a group of related projects managed in a coordinated way.
5. What is the purpose of the Perform Integrated Change Control process?
To review all change requests, approve or reject them, and manage changes across the project
in a controlled manner.
, 2. Project Scope Management
6. What is the purpose of a Work Breakdown Structure (WBS)?
It decomposes project deliverables into smaller, manageable components for planning,
execution, and control.
7. What is scope creep and how can it be prevented?
Scope creep is uncontrolled changes to the project scope. It can be prevented through a well-
defined scope statement and formal change control processes.
8. What is the difference between product scope and project scope?
Product scope defines the features and functions of the product, while project scope defines
the work required to deliver the product with those features.
9. When is the scope baseline established?
It is established after the project scope statement, WBS, and WBS dictionary are approved.
10. What is the main output of the Validate Scope process?
Accepted deliverables that have been formally approved by the customer or sponsor.
3. Project Schedule Management
11. What is the critical path in a project schedule?
It is the sequence of activities that determines the shortest possible project duration.
12. How do you calculate float in a project schedule?
Float is calculated as the difference between the latest start date and the earliest start date (or
latest finish minus earliest finish) of a task.
13. What is the purpose of a Gantt chart?
It visually represents the project schedule, showing start and finish dates, task durations, and
dependencies.
14. What is fast-tracking in schedule compression?
Fast-tracking involves performing activities in parallel that were originally planned
sequentially to shorten the project duration.
15. What is crashing in project schedule management?
Crashing is adding resources to critical path activities to reduce project duration, typically at
increased cost.