L L L L L L
Management, 9th Edition by Kathy Schwalbe
L L L L L
All Chapters 1-13 With Expert Verified Q&As Guaranteed for A+
L L L L L L L L L L
PASS
Page!!|!!1
, Chapter 1: Introduction to Project Management
L L L L L L
TRUE/FALSE
1. Until the 1980s, project management primarily focused on providing schedule and resource data to top
L L L L L L L L L L L L L L L
management in the military, computer, and construction industries.
L L L L L L L
CORRECT ANSWER: T L L
Until the 1980s, project management primarily focused on providing schedule and resource data to top
L L L L L L L L L L L L L L L
management in the military, computer, and construction industries. Today’s project management
L L L L L L L L L L L
involves much more, and people in every industry and every country manage projects.
L L L L L L L L L L L L
PTS: 1 DIF: Difficulty: EasyREF: L L p.2
OBJ: LO: 1-1NAT: BUSPROG: Technology
L L L L TOP: Introduction
KEY: Bloom's: Knowledge L
2. A difference between operations and projects is that operations end when their objectives have been
L L L L L L L L L L L L L L L
reached, whereas projects do not.
L L L L
CORRECT ANSWER: F L L
Projects are different from operations in that they end when their objectives have been reached or the
L L L L L L L L L L L L L L L L L
project has been terminated.
L L L
PTS: 1 DIF: Difficulty: Moderate L REF: p.4
OBJ: LO: 1-2 NAT: BUSPROG: Analytic
L L L L TOP: What is a Project? L L L L
KEY: Bloom's: Comprehension L
3. Every project should have a well-defined objective.
L L L L L L
CORRECT ANSWER: T L L
A project has a unique purpose. Every project should have a well-defined objective.
L L L L L L L L L L L L L
PTS: 1 DIF: Difficulty: Easy REF: L L p.6
OBJ: LO: 1-2 NAT: BUSPROG: Analytic
L L L L TOP: What is a Project?
L L L L
KEY: Bloom's: Knowledge L
Page!!|!!2
,4. Projects should be developed in increments.
L L L L L
CORRECT ANSWER: T L L
A project is developed using progressive elaboration. Projects are often defined broadly when they begin,
L L L L L L L L L L L L L L L
and as time passes, the specific details of the project become clearer. Therefore, projects should be
L L L L L L L L L L L L L L L L
developed in increments.
L L
PTS: 1 DIF: Difficulty: Moderate L REF: p.6
OBJ: LO: 1-2NAT: BUSPROG: Analytic
L L L L TOP: What is a Project?L L L
KEY: Bloom's: Comprehension L
5. Resources in a project should be used effectively because they are limited.
L L L L L L L L L L L
CORRECT ANSWER: T L L
A project requires resources, often from various areas. Resources, however, are limited and must be used
L L L L L L L L L L L L L L L L
effectively to meet project and other corporate goals.
L L L L L L L
PTS: 1 DIF: Difficulty: Moderate L REF: p. 7
L
OBJ: LO: 1-2NAT: BUSPROG: Analytic
L L L L TOP: What is a Project?L L L
KEY: Bloom's: Comprehension L
6. A project manager’s primary role is to provide the funding for a project.
L L L L L L L L L L L L
CORRECT ANSWER: F L L
A project sponsor usually provides the direction and funding for a project.
L L L L L L L L L L L L
PTS: 1 DIF: Difficulty: Easy REF: L L p.7
OBJ: LO: 1-2NAT: BUSPROG: Analytic
L L L L TOP: What is a Project? L L L
KEY: Bloom's: Knowledge L
7. One of the main reasons why project management is challenging is because of the factor of uncertainty.
L L L L L L L L L L L L L L L L
CORRECT ANSWER: T L L
Page!!|!!3
, A project involves uncertainty. Every project is unique and thus it is sometimes difficult to define its
L L L L L L L L L L L L L L L L L
objectives clearly, estimate how long it will take to complete, or determine how much it will cost. This
L L L L L L L L L L L L L L L L L L
uncertainty is one of the main reasons project management is so challenging.
L L L L L L L L L L L
PTS: 1 DIF: Difficulty: Moderate L REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Analytic
L L L L TOP: What is a Project? L L L L
KEY: Bloom's: Comprehension
L L
8. Questions about how a team will track schedule performance is related to a project’s scope.
L L L L L L L L L L L L L L
CORRECT ANSWER: F L L
Project scope deals with questions such as, ―What work will be done as part of the project?‖, ―What
L L L L L L L L L L L L L L L L L L
unique product, service, or result does the customer or sponsor expect from the project?‖, or ―How will the
L L L L L L L L L L L L L L L L L L
scope be verified?‖
L L
PTS: 1 DIF: Difficulty: Moderate L REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Technology TOP:
L L L L L What is a Project? L L L L
KEY: Bloom's: Comprehension L
9. In order to be realistic, a project manager should always set discrete goals instead of a range of
L L L L L L L L L L L L L L L L L L
objectives.
CORRECT ANSWER: F L L
Projects involve uncertainty and limited resources. Thus they rarely finish according to their original
L L L L L L L L L L L L L L
scope, time, and cost goals. Instead of discrete target goals, it is often more realistic to set a range of
L L L L L L L L L L L L L L L L L L L L
goals.
PTS: 1 DIF: Difficulty: Moderate L REF: p.8
OBJ: LO: 1-2 NAT: BUSPROG: Analytic
L L L L TOP: What is a Project? L L L L
KEY: Bloom's: Comprehension L
10. Managing the triple constraint primarily involves making trade-offs between resources and quality.
L L L L L L L L L L L
CORRECT ANSWER: F L L
Page!!|!!4