Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

DOWNLOAD YOUR CON 3990V Certification Exam Practice Questions and Answers (150 Questions with Detailed Rationales) 2026 Updated Test Bank | PDF

Beoordeling
-
Verkocht
-
Pagina's
57
Cijfer
A+
Geüpload op
31-03-2026
Geschreven in
2025/2026

DOWNLOAD YOUR CON 3990V Certification Exam Practice Questions and Answers (150 Questions with Detailed Rationales) 2026 Updated Test Bank | PDF

Instelling
CON 3990V Certification
Vak
CON 3990V Certification

Voorbeeld van de inhoud

DOWNLOAD YOUR CON 3990V Certification Exam Practice
Questions and Answers (150 Questions with Detailed
Rationales) 2026 Updated Test Bank | PDF

Q1.

A construction project owner signs a contract with a general contractor to build a
commercial structure. Which statement best describes the primary legal function of this
contract?

A. It defines only the architectural design intent without legal obligations
B. It creates a legally binding agreement establishing duties, rights, and responsibilities
between the owner and contractor
C. It serves only as a financial estimate for project budgeting purposes
D. It replaces the need for construction drawings and specifications

Correct Answer: B

 A is incorrect because contracts go beyond design intent and establish enforceable
obligations.
 B is correct because construction contracts legally define responsibilities, scope,
time, and payment obligations.
 C is incorrect because budgeting is only one part; contracts are legally binding
documents.
 D is incorrect because drawings and specifications remain essential separate
contract documents.



Q2.

In a construction dispute involving conflicting project documents, which order of precedence
is typically applied to resolve inconsistencies?

A. Shop drawings → Specifications → Contract agreement → Addenda
B. Specifications → Drawings → Contract agreement → Daily reports
C. Contract agreement → Addenda → Specifications → Drawings
D. Daily reports → Contract agreement → Specifications → Drawings

,Correct Answer: C

 A is incorrect because shop drawings are lowest in precedence.
 B is incorrect because contract agreement generally holds higher authority than
specs and drawings.
 C is correct because the contract agreement and addenda typically override
specifications and drawings.
 D is incorrect because daily reports have no contractual authority.



Q3.

A project manager identifies a sequence of activities where any delay will directly extend the
project completion date. What does this sequence represent?

A. Near-critical path with optional float time
B. Critical path determining total project duration
C. Resource leveling path for workforce optimization
D. Procurement tracking sequence independent of schedule

Correct Answer: B

 A is incorrect because near-critical paths still have float.
 B is correct because the critical path determines project duration and has zero float.
 C is incorrect because resource leveling does not define project duration.
 D is incorrect because procurement tracking is separate from scheduling logic.



Q4.

During scheduling analysis, a contractor notices that an activity can be delayed by 5 days
without affecting the project completion date. This time is known as:

A. Contingency buffer allocated by the owner
B. Free float or total float depending on dependency type
C. Critical delay requiring immediate acceleration
D. Scheduled lag imposed by regulatory authority

Correct Answer: B

,  A is incorrect because contingency refers to cost/time reserves, not activity float.
 B is correct because float is allowable delay without impacting completion.
 C is incorrect because float implies non-critical activity.
 D is incorrect because lag is a planned delay, not unused time.



Q5.

Which of the following is NOT typically included in procurement activities within construction
project management?

A. Soliciting bids from subcontractors
B. Evaluating supplier quotations and pricing
C. Developing structural engineering calculations for beams
D. Awarding contracts to selected vendors

Correct Answer: C

 A is part of procurement through tendering.
 B is part of procurement evaluation.
 C is correct because engineering design belongs to design phase, not procurement.
 D is part of procurement award process.



Q6.

A project owner issues a formal document instructing changes in scope, cost, or schedule
after contract execution. This document is called:

A. Request for information (RFI)
B. Change order
C. Bid proposal
D. Submittal register

Correct Answer: B

 A is used for clarifying design issues, not changing scope.
 B is correct because change orders modify contract terms legally.
 C is part of bidding stage, not post-contract changes.

,  D tracks submitted documents, not scope changes.



Q7.

The primary purpose of a Bill of Quantities (BOQ) in construction procurement is to:

A. Define safety procedures on construction sites
B. Provide a detailed breakdown of materials and quantities for accurate pricing
C. Replace the need for architectural drawings
D. Assign legal liability between stakeholders

Correct Answer: B

 A is unrelated to BOQ function.
 B is correct because BOQ supports pricing and tender evaluation.
 C is incorrect because BOQ complements, not replaces, drawings.
 D is handled through contracts, not BOQ.



Q8.

What is the main advantage of the Critical Path Method (CPM) in construction scheduling?

A. It eliminates the need for project budgeting
B. It identifies the longest sequence of dependent activities affecting project completion
C. It guarantees zero project delays
D. It replaces subcontractor coordination requirements

Correct Answer: B

 A is incorrect because CPM does not handle budgeting.
 B is correct because CPM focuses on schedule dependency and duration.
 C is incorrect because CPM does not prevent delays, it identifies them.
 D is incorrect because coordination is still required.



Q9.

Geschreven voor

Instelling
CON 3990V Certification
Vak
CON 3990V Certification

Documentinformatie

Geüpload op
31 maart 2026
Aantal pagina's
57
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$32.00
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
casewritters Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
99
Lid sinds
8 maanden
Aantal volgers
5
Documenten
982
Laatst verkocht
3 uur geleden

4.0

22 beoordelingen

5
12
4
3
3
3
2
2
1
2

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen