Which clause is related to Acquisition? ---------CORRECT ANSWER---------
--------52.215 - Instructions to Offerors - Competitive Acquistion
What is considered a contract action? ---------CORRECT ANSWER----------
-------Contract action means any oral or written action that results in
the purchase, rent, or lease of supplies or equipment, services, or
construction.
What is latent defect? ---------CORRECT ANSWER-----------------is one that
is not readily noticeable upon reasonable inspection at the time of
acceptance.
Who accepts the burden of latent defect? ---------CORRECT ANSWER-----
------------The burden is on the government to prove that defective
material and workmanship was the probable cause of product failure or
non-conformance.
,Who can you submit a claim to? ---------CORRECT ANSWER-----------------
Contractor claims are submitted to the KO
What is a claim? ---------CORRECT ANSWER-----------------a written
demand or assertion by one of the contracting parties seeking (i)
payment of a specific sum of money, (ii) adjustment or interpretation of
contract terms, or (iii) other relief arising under or relating to the
contract.
When is written certification for a claim required? ---------CORRECT
ANSWER-----------------When a claim exceeds $100,000, contractors
must provide the following written certification (FAR 33.207).
What are protests? ---------CORRECT ANSWER-----------------they provide
offerors with a tool to challenge federal contract award decisions.
Who do you file a protest with? ---------CORRECT ANSWER-----------------
The Government Accountability Office
,There is a janitorial contract for 2.8 million dollars for the entire base.
What FAR part would you use? ---------CORRECT ANSWER-----------------
Could be FAR Part 37 Service Contracting or Far Part 12 Acquisition of
Commercial Products and Commercial Services
What common form do you use for a modification? ---------CORRECT
ANSWER-----------------SF-30
What FAR Part is Acquisition Planning? ---------CORRECT ANSWER---------
--------FAR Part 7
What role does the Program Manager plan in Acquistion Planning? ------
---CORRECT ANSWER-----------------The PM has overall responsibility of a
contract
What is the KO's role in Acquisition Planning? ---------CORRECT
ANSWER-----------------Ensures plan is implemented and developed.
What are the three phases of a life cycle? ---------CORRECT ANSWER------
-----------Pre-award Phase
, Award Phase
Post-award phase
What are the two parts of the Pre-award phase? ---------CORRECT
ANSWER-----------------Develop Solicitation
Develop offer
Who develops a solicitation? ---------CORRECT ANSWER-----------------The
Government & The Buyer.
Who prepares an offer? ---------CORRECT ANSWER-----------------The
Contractor and the seller
During the post-award phase while the contract is being performed,
who has responsibility for quality? ---------CORRECT ANSWER---------------
--The Seller
What does the award phase involve? ---------CORRECT ANSWER-----------
------Involves all work performed by the buyer and seller