BICSI DCDC Certification Actual Exam Study Questions with Correct Answers 1. Air quality, particulate contamination, ventilation and thermal guidelines - ANSWER ASHRAE 2. Bonding - ANSWER The permanent joining of metallic parts to form an electrically conductive path. 3. Primary side - ANSWER The high-voltage side of the power service transformer, the electrical power service line side of a UPS or PDU, the 480V side of the static switch. 4. Psychological barrier - ANSWER A type of barrier that discourages unauthorized access by its presence alone. 5. RPP location - ANSWER Downstream. 6. True or False: an RPP has circuit breakers - ANSWER True 7. Switchgear - ANSWER A more elaborate switchboard used to isolate electrical equipment. Uses a segregated, insulated case and often contains monitoring and controls. 8. Typical power range for switchgear - ANSWER Ranges 800A to 5000A. 9. Trunking - ANSWER Combining, multiplexing frames. 10.Static UPS - ANSWER Non-moving, solid state components. 11.ATS - ANSWER Automatic Transfer Switch. A transfer switch that automatically transfers load conductor connections from one source to another. 12.ATS characteristics - ANSWER Self-acting. Make-before-break, maintained. 13.Transfer switch (non-automatic) - ANSWER Manual. 14.Rotary UPS - ANSWER A UPS in which the batteries (energy source) drive a motor (mover) which turns an alternator (power source), rather than being solid state. 15.X-O bond - ANSWER Point in an electrical system where a 'separately derived ground' is generated. Creates a 4th neutral conductor. 16.Building Commissioning - ANSWER Design Intent. 17.Core layer - ANSWER High-speed switching backbone. 18.Closed transition - ANSWER Circuit is 'maintained' or 'make before break'. 19.Distribution layer - ANSWER Between the core and access layer. 20.DCIE - ANSWER Data Center Infrastructure Efficiency, it is the reciprocal of PUE. 21.Formula for DCIE - ANSWER IT equipment power/Total Facility power X 100%. 22.Enclosure to prevent EMI - ANSWER A Faraday cage. 23.Fault tolerant system - ANSWER A concurrently maintainable system that is beefed-up to where redundancy is not lost during failure or maintenance. 24.LDP - ANSWER Local distribution point. 25.Common bonding network - ANSWER Refers to ALL grounding systems in a building. 26.Mesh Bonding Network (Mesh-BN) - ANSWER Refers just to that portion connecting the low-voltage equipment. 27.Open transition - ANSWER A 'break-before-make' change of state transfer where the electrical circuit is not maintained through the transfer. 28.Power strips - ANSWER To allow multiple devices to plug into the power system in a rack or cabinet. 29.Reliability - ANSWER The probability that a component or system will perform as intended over a given time period. 30.X-O bond definition - ANSWER Separate ground generated downstream. 31.MTTR - ANSWER Mean Time To Repair. 32.MTBF - ANSWER Mean Time Before Failure. 33.Dual entrance/dual pathway service feed location - ANSWER In dedicated spaces that are separate from one another, yet close to the electrical distribution spaces they serve. 34.Outdoor generators installation - ANSWER Should be installed within shelters. is preferred between Indoor and Outdoor generators - ANSWER Indoors 36.Generator exhaust location - ANSWER DOWNSTREAM of building air intakes. 37.Running hours required of a generator/fuel system at full load - ANSWER 8 to 96 hours. 38.Design multiplier for an RPP - ANSWER N X 2.0 to 3.0. 39.Multiplier Calculation: UPS and UPS critical distribution - ANSWER N X 1.25.

Meer zien Lees minder
Instelling
BICSI DCDC Certification
Vak
BICSI DCDC Certification

Voorbeeld van de inhoud

BICSI DCDC Certification Actual Exam
Study Questions with Correct Answers

1. Air quality, particulate contamination, ventilation and thermal guidelines -
ANSWER ASHRAE


2. Bonding - ANSWER The permanent joining of metallic parts to form an
electrically conductive path.


3. Primary side - ANSWER The high-voltage side of the power service
transformer, the electrical power service line side of a UPS or PDU, the
480V side of the static switch.


4. Psychological barrier - ANSWER A type of barrier that discourages
unauthorized access by its presence alone.


5. RPP location - ANSWER Downstream.


6. True or False: an RPP has circuit breakers - ANSWER True


7. Switchgear - ANSWER A more elaborate switchboard used to isolate
electrical equipment. Uses a segregated, insulated case and often contains
monitoring and controls.


8. Typical power range for switchgear - ANSWER Ranges 800A to 5000A.


9. Trunking - ANSWER Combining, multiplexing frames.

,10.Static UPS - ANSWER Non-moving, solid state components.


11.ATS - ANSWER Automatic Transfer Switch. A transfer switch that
automatically transfers load conductor connections from one source to
another.


12.ATS characteristics - ANSWER Self-acting. Make-before-break,
maintained.


13.Transfer switch (non-automatic) - ANSWER Manual.


14.Rotary UPS - ANSWER A UPS in which the batteries (energy source) drive
a motor (mover) which turns an alternator (power source), rather than being
solid state.


15.X-O bond - ANSWER Point in an electrical system where a 'separately
derived ground' is generated. Creates a 4th neutral conductor.


16.Building Commissioning - ANSWER Design Intent.


17.Core layer - ANSWER High-speed switching backbone.


18.Closed transition - ANSWER Circuit is 'maintained' or 'make before break'.


19.Distribution layer - ANSWER Between the core and access layer.

,20.DCIE - ANSWER Data Center Infrastructure Efficiency, it is the reciprocal
of PUE.


21.Formula for DCIE - ANSWER IT equipment power/Total Facility power X
100%.


22.Enclosure to prevent EMI - ANSWER A Faraday cage.


23.Fault tolerant system - ANSWER A concurrently maintainable system that
is beefed-up to where redundancy is not lost during failure or maintenance.


24.LDP - ANSWER Local distribution point.


25.Common bonding network - ANSWER Refers to ALL grounding systems
in a building.


26.Mesh Bonding Network (Mesh-BN) - ANSWER Refers just to that portion
connecting the low-voltage equipment.


27.Open transition - ANSWER A 'break-before-make' change of state transfer
where the electrical circuit is not maintained through the transfer.


28.Power strips - ANSWER To allow multiple devices to plug into the power
system in a rack or cabinet.


29.Reliability - ANSWER The probability that a component or system will
perform as intended over a given time period.

, 30.X-O bond definition - ANSWER Separate ground generated downstream.


31.MTTR - ANSWER Mean Time To Repair.


32.MTBF - ANSWER Mean Time Before Failure.


33.Dual entrance/dual pathway service feed location - ANSWER In dedicated
spaces that are separate from one another, yet close to the electrical
distribution spaces they serve.


34.Outdoor generators installation - ANSWER Should be installed within
shelters.


35.which is preferred between Indoor and Outdoor generators - ANSWER
Indoors


36.Generator exhaust location - ANSWER DOWNSTREAM of building air
intakes.


37.Running hours required of a generator/fuel system at full load - ANSWER 8
to 96 hours.


38.Design multiplier for an RPP - ANSWER N X 2.0 to 3.0.


39.Multiplier Calculation: UPS and UPS critical distribution - ANSWER N X
1.25.

Geschreven voor

Instelling
BICSI DCDC Certification
Vak
BICSI DCDC Certification

Documentinformatie

Geüpload op
2 april 2026
Aantal pagina's
51
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$11.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
DrSammuel

Maak kennis met de verkoper

Seller avatar
DrSammuel TeachmeTutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
4
Lid sinds
4 maanden
Aantal volgers
0
Documenten
660
Laatst verkocht
2 weken geleden
Turning Preparation into Achievement.

Welcome to my study resource hub! This account provides high-quality exam papers with clear and detailed elaborations designed to help students fully understand each topic and pass with confidence.

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen